The Constitution of Mozambique establishes under Article 98 that “the natural resources located in the soil, subsoil, inland waters, territorial sea and continental shelf, as well as in the exclusive economic zone, are the property of the State”, and also that the law (ordinary law) regulates the management and conservation of all assets of public domain. In other words, all oil and gas resources belong to and are managed by the state.
The oil and gas legislation regulates how private entities explore petroleum resources, noting that any operation must be previously authorised by the state, through an administrative authorisation or a licence. The government reserves the right to be part of any project implemented to conduct petroleum operations, through state-owned company Empresa Nacional de Hidrocarbonetos, EP (ENH).
The council of ministers is the highest government body with competence to approve primary sector legislation and grant concessions, including the approval of the respective contracts.
The Ministry of Mineral Resources and Energy (MIREME) is the government body that steers and monitors the implementation of government policy in the geological investigation and exploitation of minerals and energy resources, including coal and hydrocarbons, and the development and expansion of electricity supply infrastructure, natural gas and petroleum products. It performs day-to-day governance, implements oil and gas sector policies, and is also responsible for the supervision of the National Institute of Petroleum (INP).
The INP, created through Decree No 25/2004, of 20 August 2004, manages and oversees Mozambique’s petroleum resources in its role as a national agency, and is the regulatory entity responsible for the administration, promotion and supervision of petroleum activities. It is responsible for the guidelines for the participation of the public and private sectors in the prospecting and exploration of petroleum products and their derivatives, and for the regulation and control of operations and tender procedures, while guaranteeing the preservation of public interest and the protection of the environment.
The High Authority for the Extraction Industry (HAEI) was created by the Petroleum Law, with the purpose of supervising petroleum activities in Mozambique. However, it has not yet become operational, given that its composition, status, powers and organisational structure have not been defined by the council of ministers.
The state-owned company ENH is the entity responsible for the prospecting, exploration, production and commercialisation of petroleum products, representing exclusively the Mozambican state in all petroleum operations.
ENH participates in all petroleum operations and stages, and manages the oil and gas quotas destined for the development of the national market and the country's industrialisation.
Any investor interested in the exploration of petroleum resources in Mozambique will enter into a partnership with ENH. The Petroleum Law determines that the government ensures the financing of ENH.
The principal petroleum laws and regulations in force in Mozambique are as follows.
Private investment in upstream interests for conducting petroleum operations is granted through concession contracts, which are generally attributed through a public tender process. Such rights may also be attributed by simultaneous or direct negotiations in relation to areas that have already been declared available.
Concession contracts are administrative contracts, subject to the supervision of the administrative court, which includes the need for its previous authorisation and the publication of its main clauses in the official gazette.
The following rights may be conferred under concession contracts:
Note that the EPCC is the key contract applicable to upstream activities, as it grants an exclusive right to carry out petroleum exploration and production.
As a first step, the INP defines which areas within Mozambican territory are available, then launches a public tender for those interested to submit their bids for the exploration of such areas. A list of prerequisites is provided, as well as guidelines for the preparation of applications and the bidding criteria. This information can be found on the INP’s website.
The bids are evaluated according to aspects relating to health, safety and the environment (HSE), financial capacity, technical competence/capability and the economic terms offered to the Mozambican state.
Companies carrying out petroleum operations (either upstream or downstream) need to obtain the relevant licence for the activity to be carried out, which may include one (or more) of the following (without prejudice to others that may be necessary and are not listed below):
The typical fiscal terms for upstream activities encompass a combination of corporate income tax and royalty-based taxation, in addition to bonus payments, training programmes, relinquishment funds and other financial obligations set out in the concession contract.
Concessionaires are generally subject to petroleum production tax ("IPP") and to the specific rules of corporate income tax ("IRPC") and the mechanisms of production-sharing, with the latter drawing on the traditional concepts of cost petroleum, available petroleum, profit petroleum and produced petroleum.
A percentage of the income generated by petroleum operations must be allocated to the community in the area where the petroleum operations are undertaken. The percentage payable is established by the state budget law.
The IPP payment is triggered when the oil or gas is extracted, and the applicable tax rates are 10% for crude oil and 6% for natural gas. These rates are reduced by 50% when the production of oil and gas is destined to be used by local industry (the IPP tax rate then being 5% for crude oil and 3% for natural gas).
In addition, the tax regime provides tax stability for ten years, subject to an additional payment of 2% for IPP, effective from the 11th year of production.
Entities that are entitled to perform petroleum operations are subject to the following general taxes:
Such entities are also subject to the specific petroleum tax regime, which levies IPP on oil and gas produced in each concession area.
IPP
IPP (which is equivalent to a royalty) is due on the value of the oil and gas produced in Mozambique at the development and production site, with the taxable base being the value of petroleum produced determined on the basis of the weighted average price of sales by the producer and respective contractors in the month to which the tax corresponds.
IPP becomes payable when the petroleum produced enters the measuring station, as defined in the concession contract. It is generally paid in cash and may be paid partially or fully in kind, at the option of the government.
IRPC
Specific rules relating to IRPC cover ring-fencing, cost definition, depreciation rates, capital gains taxation and the mechanisms for production-sharing with the government.
The standard IRPC rate is 32%, applicable to companies and similar corporate entities (petroleum operators included) for income generated in Mozambique and abroad (worldwide income).
Ring-fencing rules set forth that the IRPC of entities undertaking petroleum operations under a concession agreement should, as a general rule, be calculated individually for every concession area (costs and income should also be determined separately in relation to each area), and each concession agreement area must have its own taxpayer number (NUIT).
Capital Gains Tax
All capital gains arising from the direct or indirect transfer of petroleum rights, between non-resident entities with or without permanent establishment in Mozambique, are taxed at 32%. This capital gains tax is due from the seller or transferer, but the purchaser and the Mozambican entity holding the petroleum rights have several and joint liability for the payment of the tax. This provision mainly entails that gains resulting from the direct or indirect transfer between non-resident entities of shares or other participating interests or rights involving assets located in Mozambican territory, whether for a consideration or not, are regarded as income obtained in Mozambique, irrespective of the place where the transfer occurs.
Customs Duties
Exemption from custom duties for a period of five fiscal years (from the date of approval of the development plan) is provided for in the law, in particular on the importation of capital goods to be used in petroleum operations.
Withholding Tax
A withholding flat tax rate of 10% applies on the payment of services related to concession agreements undertaken by non-resident entities.
Costs
Exploration costs are considered to be a cost in the financial year in which they are incurred, subject to special provisions in concession contracts. Provisions created by companies involved in the petroleum-extracting industry relating to the reconstruction of wells can be deducted for tax purposes, in addition to those provisions designed for the recovery of the landscape and environment of the exploration site after the conclusion of the work being undertaken.
Costs incurred by the concessionaire on petroleum operations, excluding interest and other financial costs, are recovered from 60% of the annual available petroleum; the portion exceeding this limit is transferred to the following years.
Profit Oil
Profit oil is shared between the government and the concessionaire according to a variable scale, the result of which is obtained through a mathematical formula.
As explained in 1.3 National Oil or Gas Company, the government reserves the right to participate in petroleum operations through ENH, and any investor interested in exploring Mozambican oil resources must proceed in association with ENH. No indication is given in the law as to what ENH’s equity stake would be in the relevant joint venture.
The General Oil and Gas Legal Framework
According to the general oil and gas legal framework, holders of oil and gas titles and exploitation rights (upstream or downstream) must give preference to local products and services whenever these are comparable to foreign products and services in terms of quality standards, and whenever the local products and services offered by Mozambican individuals or entities do not exceed the price of imported goods by more than 10% (including taxes).
In addition, foreign companies wishing to provide services and goods to oil and gas title-holders must have an association with Mozambican natural or legal entities in order to be able to do business in Mozambique.
As for the employment of foreign workers, it is important to reiterate that the basic principle is that Mozambican workers must be hired in preference, and an extensive and well-detailed training programme must be put in place by the operators to develop the local workforce.
In relation to reinsurance or captive insurance relating to petroleum operations, construction or facilities, concessionaires must give preference to Mozambican insurance companies, if the insurance available locally is comparable to international standards and the prices do not exceed the price of comparable insurance coverage on the international market by more than 10%, inclusive of taxes and related fees.
The government should ensure that no less than 25% of the oil and gas produced in the national territory is destined for the national market, and should regulate the acquisition, price and other matters integral to the use of the aforementioned oil and gas quota.
Projects in the Rovuma Basin
In relation to projects in the Rovuma Basin, the following local content requirements apply:
Local Content Plan
The Local Content Plan will be drawn up in conformity with the following principles:
The concessionaires and SPEs may adopt different rules in connection with the acquisition of goods and services in respect of projects totally or partially financed by an agency providing credit for exports, in so far as the adoption of different rules is expressly provided for as a condition in such financing contracts.
Reporting to the INP
Operators must report all discoveries to the INP within 24 hours of their detection, and the INP must be kept informed of the test results and evaluation of the commercial discovery, based on an appraisal programme undertaken by the operator to evaluate the discovery. Within six months of completing the appraisal programme, the operator must submit an appraisal report containing the results of the activities performed and their evaluation.
Contacting the MIREME
Within one year of the submission of the appraisal report, the operator may contact the MIREME to confirm whether the petroleum deposits covered by the discovery may be commercially developed. This notification must include a Declaration of Commerciality, comprising a complete description of the relevant data, surveys and evaluations that led to such conclusions, which will constitute the basis for the government's decision as to whether it will exercise the option to participate in the development and production of the petroleum deposits.
Submission of a Development Plan
As a next step, a development plan must be submitted to the INP within one year of the issuance of the Declaration of Commerciality. The development plan and its implementation must be based on the rational use of petroleum reserves and existing facilities. The production of petroleum from multiple zones with reserves through a sole line of production will only be authorised if that method of production is necessary to render the production commercially profitable.
The INP will be consulted on the scope and content of the development plan, which must consider the respective economic, technical, environmental, safety and existing resources.
The approval of a development plan for a petroleum deposit that covers more than one EPCC area will be contingent upon the execution of a unitisation contract by the respective operators.
The appeal of any decisions taken by the government may be conducted through the administrative courts.
Reconnaissance Concession Contract
The reconnaissance concession contract grants the non-exclusive right to carry out preliminary exploration work and assessment operations in the concession contract area. This contract is executed for a maximum period of two years, is non-renewable, and permits the drilling of wells to a depth of 100 m below the surface or at the bottom of the sea.
EPCC Contract
The EPCC contract grants an exclusive right (that will not exceed eight years) to carry out petroleum exploration and production, as well as a non-exclusive right to construct and operate oil or gas pipeline systems for the transportation of crude oil or natural gas, or infrastructure for the liquefaction of gas produced from the concession contract area, except where access to an existing oil pipeline or gas pipeline system or other existing infrastructure is available on reasonable commercial terms.
An extension may be granted of up to two or eight years respectively, upon discovery of resources, depending on the efforts needed to conduct an appraisal programme or a commercial evaluation of the discovery.
Other Concession Contracts
The oil or gas pipeline system concession contract must be accompanied by the relevant development plan and grants the right to construct and operate oil or gas pipeline systems for the purpose of transporting crude oil or natural gas in those cases where such operations are not covered by an EPCC.
The construction and operation of petroleum infrastructure grants the right to construct and operate infrastructure for petroleum operations, such as processing and conversion, which are not covered by an approved exploration and production development plan. The construction and operation of an oil or gas pipeline system, as well as the concession and operation of infrastructure, are enabled through a concession contract following a public tender.
Any concession contract may terminate following total relinquishment of the contract area, rescission or abandonment.
The transfer of interests in upstream licences attributed under a concession contact is subject to government approval and must observe Mozambican law. Such government approval is also necessary for the direct or indirect transfer of the participation interest in the concession agreement, including through the assignment of shares or any other form of ownership stake of the entity holding the concession rights.
There are currently no legal restrictions on the production of petroleum.
The Rules on Import, Export, Distribution, Storage and Transport of Oil Products
The activities and facilities related to the receipt and transport by pipeline of crude oil or other raw materials used in the production of petroleum products, as well as the storage and transport of crude oil, including local production, except with regard to the attribution of rights for petroleum operations under the terms of the applicable legislations in the geographical areas covered by such rights, are set out under the Rules on Import, Export, Distribution, Storage and Transport of Oil Products.
The Distribution and Trade of Piped Natural Gas
The distribution and trade of piped natural gas and the international transit service are governed by specific legislation.
Liquefied petroleum gases (LPG), car fuels, aviation and illumination fuels and fuel oils are imported by a single private entity, Importadora Moçambicana de Petróleos, Limitada ("IMOPETRO"), which is the designated Liquid Fuels Purchases Operator. The acquisition of fuel products using government credits or donations is also carried out through IMOPETRO, with certain exceptions. The potential suppliers are chosen through international public tender.
The national retail oil company – Petróleos de Moçambique, SA ("PETROMOC") – holds 51% of the share capital of IMOPETRO, and authorised operators hold shares in proportion to their stake in the domestic market.
IMOPETRO is supervised by the Commission for the Purchase of Liquid Fuels ("CACL"), an entity established with the purpose of ensuring transparency and competitiveness in the processes of purchasing liquid fuels and any petroleum products, using government donations or credits.
IMOPETRO's functions include drawing up purchase plans and proposals for revision, preparing tender documents, launching tender processes, evaluating proposals, proposing the selection of suppliers, and negotiating and assigning contracts for the financial intermediation of acquisitions, among others.
IMOPETRO may charge the distributors a commission to cover functioning expenses and to ensure the repositioning of investments that are necessary for the performance of its attributions.
IMOPETRO cannot, inter alia, pursue the activity of production, distribution or commercialisation of oil products, nor can it hold equity in any company or make financial commitments that are not directly connected to its attributions.
The following rights (under a licence) may be granted to private investors:
The aforementioned licences are generally granted by the MIREME.
An entity may hold more than one of these licences, as long as that does not affect the development of competitive markets for petroleum products in accordance with the activities the entity pursues. Notwithstanding this, the holder of a distribution licence cannot hold a retail licence, except in the case of liquid gas and compressed natural gas, and except for the operation of a sole point of fuel supply for the purposes of training in each of the country's provinces.
The retail licence covers the exercise of retail activities in storage centres, the exercise of retail activities at a fuel station and the exercise of retail activities at resale stations.
Downstream licences are granted upon application to the competent authority by the interested party and include the following:
Any application for downstream activities licences must include the following principal documentation:
Special requirements and terms of service will depend on what type of operation is being licensed.
The production licence application must include the following:
The application for a storage licence in distribution terminals, in storage facilities and the exploration of unloading terminal licence must include a description of the prices and tariffs for each service being rendered at the relevant facilities. Entities holding storage licences have an obligation to receive, dispatch, handle, store, mix or conduct – without discrimination and in acceptable commercial terms – a third party's fuel-related products in their facilities, as long as they have enough technical capacity, and provided that the products are technically compatible.
Any holder of a distribution licence may only sell the petroleum products mentioned in the respective licence to holders of a supply point retail licence, to holders of a retail licence in central storage facilities and to holders of a registration document for consumer facilities. These are banned in quantities of less than 400 litres of liquid fuels and 110 kg of LPG per delivery or capacity of recipient.
Distributors are specifically required to keep a permanent reserve of petroleum products in storage in the national territory, specifically at an ocean facility in each region in which they operate.
The holder of a licence for retail at a fuel station may only sell the petroleum products mentioned in the respective licence to end-users, and may only acquire petroleum products from a licensed distributor with which it has entered into a supply contract.
The construction of any petroleum facility is subject to authorisation, which must be made in co-ordination with the entity responsible for the registration of the facility.
The MIREME is responsible for overseeing the processes for special importation authorisation and for granting special importation authorisation to entities.
Charges and Registration
Charges for licensing vary between MZN1 million and MZN900 million. In addition to the licensing charges, applicants for licences are liable for a payment of a geographic incentive fee of MZN6 million, charged on the basis of location and the number of installations and equipment.
Before beginning the exploitation of any petroleum facility and/or equipment, the owner must request an inspection of the facilities and/or equipment for the purposes of registering with the competent entity.
The owner of a facility must communicate in writing to the licensing entity, within a period of 15 working days, the occurrence of any event that leads to any amendment of the registered information relating to the facilities.
Maximum sale prices for petroleum products for consumption on the national market are established in the national currency per standard parameter of unit measure, as per the following sequence:
Costs
The base cost for each product is the cost of the imported product at the distribution terminals, located at the port of Maputo (Lingamo-Matola) for LPG and at the ports of Maputo (Lingamo-Matola), Beira or Nacala for the remaining products.
The base price for each petroleum product is the carriage and insurance paid (CIP) price at the distribution terminals, which includes port or docking expenses related to the product or tanker, demurrage costs, commissioning, unloading losses and other related expenses, whenever they are not included in the calculation of the importation-related costs component.
The importation-related costs component represents the value for covering the losses related to the acquisition, disembarkation, handling, transport and reception of the petroleum products, at the distribution terminals.
DSP
The DSP for each product is the maximum price of bulk sale to the distribution terminals' address used by the distributors, and is calculated from the sum of the base cost, the distributor's margin, and the fiscal charges in force.
When supply to the distributors is not carried out in bulk (considered a quantity of product that is greater than or equal to 400 litres per delivery, item of packaging or container), packaging costs may be added to the DSP.
PSP
The PSP for each petroleum product is the maximum price to be employed at points of sale and points of storage of liquid fuels, located in the municipalities of cities with distribution terminals.
Prices of any petroleum product will be revised monthly, and updated and communicated to the duly licensed distributors on the third Wednesday of each month (or, if that is a bank holiday, on the working day immediately following it), wherever the respective base cost has a variation greater than 3% compared to the in-force base cost on the date of calculation, or where there is an alteration in the applicable fiscal charges.
It is up to the ministers responsible for the energy and finance sectors to proceed with the alteration of the prices of petroleum products, provided that the PSP of any product does not vary by more than 20% compared to the in-force price. The council of ministers is responsible for the alteration of the prices of petroleum products wherever the variation in the PSP of any product is greater than 20% compared to the in-force price.
Please refer to 2.4 Income or Profits Tax Regime Applicable to Upstream Operations.
Please refer to 3.1 Forms of Allowed Private Investment in Midstream/Downstream Operations and 3.2 Rights and Terms of Access to Any Downstream Operation Run by a National Monopoly.
Please refer to the requirements listed under 2.6 Local Content Requirements Applicable to Upstream Operations.
Please refer to 3.3 Issuing Downstream Licences.
Pursuant to the Mozambican constitution and the fundamental principle of Mozambican law, all land belongs to the state. Therefore, an entity (whether Mozambican or foreign) cannot be the owner of the land where any infrastructure is implemented, but may be granted the right of use and enjoyment of the land ("DUAT") for a 50-year renewable period.
The holder of the DUAT becomes the owner of any infrastructure built on the land to which the DUAT relates and may sell the immovable property built on the land by means of a public deed. With the sale of the immovable property, the DUAT is automatically transferred to the acquirer of the property.
The holders of distribution, landing terminals, storage or oil pipeline licences are obliged to receive, issue, handle, store, mix or manage third-party petroleum products at their petroleum storage facilities, landing terminals or oil pipelines, without discrimination and in non-discriminatory commercial terms, provided that there is available space at the petroleum facility concerned and there are no insurmountable technical problems that impede the use of the petroleum facility to meet the requirements of third parties.
Obligatory Modifications
If the available capacity of the petroleum facility concerned or the dimension or route of pipelines is insufficient to meet the requirements of third parties, the licence holder is obliged to make a modification to the facility so that third-party requests can be met in commercially acceptable terms, provided that such modification does not have an adverse effect on the technical integrity or safe operation of the petroleum facility. The requesting third parties must ensure sufficient funds to support the costs of the required modification.
The MIREME may waive compliance with the obligation described above if reasonable efforts have been made to meet the requirements of third parties and to prove that it is not possible to receive, send, handle, store, mix or manage the third-party petroleum products or carry out the requested modification of the petroleum facility.
Negotiation of Terms
The holders of licences or the operators of the petroleum facilities must make available, in non-discriminatory terms, the relevant records on the petroleum facility in question to third parties who request it, in order to facilitate the negotiation of acceptable commercial terms.
If the parties have not reached an agreement on the commercial or operational terms that ensure the access sought within six months of the notification of the request for access to the petroleum facility or to increase its respective capacity, depending on the terms of the contract, the matter may be submitted for resolution to an independent commission, to arbitration proceedings, or to the competent judicial authorities.
Reserve of Capacity
In addition to its needs for supply to the national market, the entity in possession of storage infrastructure in the ocean terminals must reserve at least 15% of its capacity for third-party access to products for the national market.
The local petroleum products market must primarily be supplied with products from local production, as long as:
The import of petroleum products can only occur when the options referred to in the previous paragraph are exhausted.
Any written or tacit agreement between market participants for the supply of petroleum products for national consumption or for the use of a dominant market position to obtain operational margins above those that would result from a competitive market situation, or that results in the prevention or reduction of competitiveness in processes related to the purchase of petroleum products, is prohibited and will be penalised under the terms of the applicable legislation.
As indicated in 2.6 Local Content Requirements Applicable to Upstream Operations, the Petroleum Law determines that the government must make sure that 25% of the oil and gas produced in Mozambique is allocated to the national market, upon regulation of the acquisition, price and matters inherent to the use of that quota. Also, oil companies are obliged to give the state preference in the acquisition of the oil produced, whenever national interests are raised.
That said, the exportation of petroleum products is subject to licensing. Entities wishing to distribute petroleum products may provide bunker services for the re-exportation of those products, as long as such activities are accompanied by a sale in the national market too.
In turn, foreign entities based abroad that wish to conduct such activities from Mozambique, for the international shipping of products coming from Mozambique, or that wish to transport such products within the neighbouring countries, must request a specific licence.
For further information, see 3.3 Issuing Midstream/Downstream Licences.
All downstream licences are transferable, subject to written authorisation from the licensing entity, with the exception of distribution licences.
The transfer of the property of petroleum facilities that may result from their sale or disposal, or from the exercise of any commercial agreements, mergers or any other transactions between two or more entities, requires authorisation from the MIREME. Such authorisation shall be granted if, having considered the participation of the parties involved in the petroleum products market and the share of that market associated with the facilities and equipment in question, it is verified that none of the parties involved is obtaining or may obtain more than a 30% share of the national market for petroleum products as a direct result of the respective transfer, or is increasing or may increase its share of the national market for petroleum products if it already has more than a 30% share.
The MIREME may authorise the transfer of a petroleum facility property that exceeds the limits imposed in the previous paragraph if the beneficiary of the transfer is duly licensed to operate in the national petroleum product market and is at least 51% owned by the Mozambican state.
Foreign investment is regulated by the Investment Law, the Regulation of the Investment Law and the Code of Fiscal Benefits. Foreign investors – individuals or corporate entities bringing their own capital and resources to Mozambique from abroad, on their own account and at their own risk – may be granted a specific (free) exchange control regime, provided that some conditions are met. They may be eligible for tax incentives, such as deductions from taxable income, deductions from the amount of tax assessed, accelerated depreciation, tax credits, exemption from tax and a reduction of the rate of taxes and other fiscal payments, the deferment of the payment of taxes and other special fiscal measures.
Foreign direct investment (FDI) in petroleum, both national and from abroad, may, solely or jointly, be made as follows if quantifiable in pecuniary terms:
The government will grant the guarantees described below to investors that have obtained investment project authorisation, in accordance with foreign investment legislation:
The Petroleum Law specifically provides for the legal safety and protection of property over assets and rights, including industrial property rights within the scope of authorised and operated investments in petroleum activity.
In addition, expropriation may only occur exceptionally and when substantiated with regard to public interest, and is subject to the payment of fair compensation. All rights obtained under concession agreements relating to petroleum operations entered into under the previous Petroleum Law are to remain valid and unaffected by the Petroleum Law currently in force. Upon termination of these agreements, new contracts and concessions are to be executed under the terms of the present law.
Mozambique is a signatory to ICSID and the Washington Convention of 15 March 1965 on the Settlement of Investment Disputes between States and Nationals of Other States, and is a member of the ICC and a signatory to the Additional Facility Rules of ICSID approved on 27 September 1978. Mozambique also became a signatory to the New York Convention on the Recognition and Execution of Foreign Arbitral Decisions on 10 July 1998, which is fully applicable in the national territory. However, as permitted by Article I (3) of the New York Convention, when it acceded thereto, Mozambique declared that it would apply the Convention to the recognition and enforcement of awards made only in the territory of another contracting state, on the basis of reciprocity. In accordance, the Petroleum Law specifically provides for arbitration between the state of Mozambique and foreign investors to be conducted in accordance with:
Furthermore, Mozambique is party to several bilateral investment treaties (BITs) with key nations, generally to promote and strengthen investment relations between Mozambique and other countries. All these BITs aim to foster FDI into Mozambique, providing investors with guarantees and protection measures (security and protection of property rights, access to foreign loans and loan repayment, remittance of dividends, arbitration by the ICC or ICSID for dispute resolution, liberalised banking rates), but they do not overcome or provide protection from foreign ownership restrictions imposed under sector-specific legislation.
This does not apply in Mozambique.
The Constitution of the Republic of Mozambique specifically addresses matters relating to the environment and quality of life, and grants the people of Mozambique the right to live in a balanced environment. It commits the state and local authorities, in collaboration with other appropriate partners, to adopt policies for the protection of the environment and to care for the rational utilisation of natural resources.
The principal environmental laws governing upstream and downstream operations are as follows:
In accordance with the nature, size and geographical location of the petroleum operation to be carried out, the MIREME may create an inter-institutional group.
The Ministry of Land, Environment and Rural Development, established by Presidential Decree No 13/2015, of 16 March, is in charge of supervising the environmental sector and compliance.
Environmental impact assessments, including impact reduction measures, must be carried out in all areas that may be affected before commencing a major petroleum project. In addition, all environmental aspects influenced by petroleum operations must be recorded in a registry to be maintained during all phases.
For the purposes of categorisation of petroleum operations, activities are usually classified as follows:
There are two other categories (B and C), which do not relate to petroleum operations.
As a rule, any activity that may affect the environment is subject to evaluation of its potential impact, through an EIS. If it is determined to be environmentally feasible, it will be issued with an environmental licence.
Activities in areas and ecosystems meriting special protection under national or international law, such as coral reefs, are specifically classified as Category A+ activities under the environmental legislation, and therefore require a full EIS and the issuance of an environmental licence as a prerequisite for the issuance of any other licence or permit that may be legally required.
The EIS initiates with the submission of an application to the Ministry for Co-ordination of Environmental Affairs (or the Provincial Delegation) and follows various stages, including a pre-assessment, drafting of terms of reference, a public consultation process and an environmental impact report.
In accordance with maritime legislation, the MIREME may introduce other requirements related to the performance of petroleum activities by floating facilities or by vessels, independent of whether they are registered in Mozambique or in a foreign state.
The holder of rights under the Petroleum Law must act in a safe and efficient manner in petroleum operations, with the aim of ensuring that polluted water and waste materials are disposed of in accordance with approved methods, and ensuring the safe closure and decommission of all holes and wells before abandonment.
There are no specific rules that apply to offshore development.
In accordance with Mozambican legislation and internationally accepted marine standards, as a general rule, floating or fixed facilities used offshore must be designed and equipped in such a manner as to ensure the stability or foundation necessary for their safe operation and the capacity to withstand the projected loads.
The docking gear, anchorage system and dynamic positioning system for ships or floating facilities used offshore shall be sized and operated in accordance with the Mozambican legislation in force and with good oilfield practices and internationally accepted marine standards.
The EIS report must also take the decommissioning and rehabilitation plan into consideration.
A specific fund must be constituted by the concession holders for the abandonment and decommissioning of infrastructure. Accordingly, pursuant to the Petroleum Law Regulation, a detailed decommissioning plan must be prepared in consultation with the INP and submitted for the MIREME's approval at least two years prior to the date on which production operations are expected to cease.
The decommissioning plan must include the following information:
In parallel, and 120 days before the decommissioning activities begin, a licence must be obtained from INP, which will be valid for the duration of the decommissioning plan. The decommissioning activities are also subject to the INP’s supervision, which includes assessing if all environmental damage has been duly repaired.
There is no specific legislation regulating climate change. For legislation on environmental protection, see 5.1 Principal Environmental Laws and Environmental Regulator(s).
The Mozambican state has the right of expropriation of concessions due to national interest, and investors would be entitled to fair compensation, to be determined on a case-by-case basis.
When it comes to environmental protection, the investor also has the obligation of complying with the mandatory environmental protection rules. Upon breach of these rules, the Mozambican government may impose fines and ultimately revoke the rights attributed to the investors.
There is no specific legislation regulating unconventional upstream interests in Mozambique.
Mozambique’s Special Regime for Natural Gas Liquefaction Projects in Areas 1 and 4 of the Rovuma Basin (Decree Law No 2/2014, of 2 December) applies to concessionaires under existing EPCCs, any SPVs established by such concessionaires and any persons entering into contracts with concessionaires or SPVs (contractors, financiers and employees), as well as their subcontractors, in connection with activities relating to the development and operation of Offshore Areas 1 or 4 that are undertaken under existing EPCCs, or any other contracts with the government of Mozambique.
Any SPVs established by concessionaires must be incorporated in Mozambique, although SPVs for the purposes of raising finance or undertaking sales and shipping activities may be incorporated in any "transparent" jurisdiction where the government of the jurisdiction can verify the ownership, management, control and fiscal situation of the investor (subject to Mozambican government consent). While this transparent jurisdiction standard is equivalent to the standard imposed on new concessionaires under the Petroleum Law, unlike the requirements of the Petroleum Law, neither the existing concessionaires of Areas 1 and 4, nor their SPVs, are required to be listed on the Mozambican Stock Exchange.
The former prime minister of Mozambique, Carlos Agostinho do Rosário, speaking at COP26 in Glasgow in November 2021 declared, “Mozambique is determined to continue its efforts to reach, by the year 2030, the levels of 62% of renewable energy contribution in the national energy matrix within the scope of achieving the Sustainable Development Goals.”
Natural gas is considered to be a crucial element for the energy transition in Mozambique and for the transformation of the country’s economy and people’s lives. Current expectations are that gas will be a catalyst for economic development and an opportunity to finance both the energy transition and the diversification of energy sources, using its revenues to leverage other sectors of the economy such as tourism and agriculture.
Citing the minister of economy and finance, Max Tonela, “Mozambique has proven reserves of over 180 trillion cubic feet of natural gas that can and should be used to contribute to reducing and mitigating the situation in this transition process and [it] will be an important player in the production and export of natural gas, contributing to energy transition in Mozambique, but also in the world.”
Furthermore, Mozambique's current Natural Gas Master Plan is drafted in such a way as to accommodate and allow future use of gas for the transformation of the economy of southern African countries.
Projects are also currently in the pipeline for the transformation of gas into liquid to facilitate transportation to markets such as Europe, Asia and other countries on the African continent.
Mozambique 6th Licensing Round for Hydrocarbon Exploration and Production Areas was launched in November 2021 in Maputo, with 12 companies pre-qualified: six as operators and the remaining six as non-operators.
Mozambique’s petroleum industry is set to develop exponentially in the coming years due to the discovery of huge natural gas deposits in the north of the country, in the province of Cabo Delgado in Area 1 and Area 4.
Area 1
Area 1 is being developed by a Total-led consortium and follows a final investment decision of USD25 billion taken in 2019, for the construction and operation of a 12.88 million tonnes per annum (Mtpa) onshore liquefied natural gas facility. In April 2021, Total and its partners declared a force majeure, due to insurgency attacks in Afungi, northern Cabo Delgado Province, and activities in the region have been suspended, with no indication of when these will resume.
Area 4
Under the second area, Area 4, there are currently two main projects, Coral South FLNG and Rovuma Liquefied Natural Gas (Rovuma LNG). The first is located offshore and is the first FLNG project in Africa, developed and operated by ENI, which started construction in September 2018, and is estimated to reach a production of 3.4 million tonnes (Mt) of LNG a year, starting from mid-2022.
The second project, Rovuma LNG, is being developed by Mozambique Rovuma Ventures (MRV), a joint venture between ENI, ExxonMobil and CNPC. It consists of a 15.2 Mtpa LNG export facility planned to be developed to liquefy and market gas resources from three reservoirs in the Area 4 block of the Rovuma Basin, offshore Mozambique.
The final investment decision on the multibillion-dollar Rovuma LNG project was expected in the first half of 2020 (followed by construction works), but no such decision has occurred as yet.
Both projects will boost the development of infrastructure in the province of Cabo Delgado and the exploration of gas. The government is engaged in promoting the exploration of these resources and has designated this as one of the top priorities as sectors to look at to allow for the development of the Mozambican economy.
Other Fields
Besides the two projects identified above, Sasol continues to develop other fields in the south of Mozambique (Pande and Temane), exporting gas through a pipeline to South Africa.
There has not been any material change in the oil and gas legal framework in Mozambique over the past year.