Legal Framework
The principal laws governing New Zealand's construction industry are found in statutes and common law authorities. Common law authorities from similar overseas jurisdictions are not binding in New Zealand, but are often influential.
Key Statutes
Building Act 2004
This is the primary legislation governing the building industry. Its stated purpose is to provide that people can use buildings safely and without endangering their health. This act:
Construction Contracts Act 2002
This act is predominantly concerned with regular and timely payments between the parties to a construction contract, given the importance of cash flow for contractors. This act:
Health and Safety at Work Act 2015
This act outlines the standard needed at work sites to ensure personnel are safe. The act also controls how this standard is measured and enforced.
Resource Management Act 1991
This act promotes the sustainable management of natural and physical resources. A construction project needs Resource Consent to demonstrate the work does not adversely impact the environment. The act regulates this process and requirement.
There are no mandatory contracts for construction projects in New Zealand. However, there are common and standard form New Zealand contracts for construction and for key construction consultants.
The New Zealand Standard (NZS) Series of Construction Contracts
The two most common standard form contracts for construction are provided by Standards New Zealand.
NZS 3910:2013 – Conditions of contract for building and civil engineering – Construction
This is a "construct only" contract where the employer provides the design and the contractor is responsible for the construction component of the project.
NZS 3915:2005, which is a similar "construct only" contract, is sometimes used instead of NZS 3910:2013 on projects where there is no "engineer" (see 2.1 The Employer).
NZS 3916:2013 – Conditions of contract for building and civil engineering – Design and construct
This is a "design and build" contract where the employer provides its requirements and the contractor is responsible for both the design and the construction of the project.
Design, which is the key distinction between NZS 3910:2013 and NZS 3916:2013, is discussed further in 3.3 Design.
Other Standard New Zealand Construction Contracts
Other standard form contracts that are found in New Zealand include the following.
The New Zealand Institute of Architects (NZIA) forms of contract
The Registered Master Builders Association forms of contract
Overseas Forms of Construction Contracts That Are Commonly Used in New Zealand
Several overseas forms of contract are commonly used for construction projects in New Zealand including:
a) The "Red Book" – Conditions of contracts for construction;
b) The "Yellow Book" – Conditions of contracts for plant and design-build; and
c) The "Silver Book" – Conditions of contracts for engineering, procurement and construction (EPC)/turnkey.
Standard New Zealand Construction Consultancy Contracts
The most common forms of consultancy contract for construction professional services are:
The Impact on Standard Form Contracts
Few standard form contracts in New Zealand anticipated an event as far-reaching as the pandemic, so parties now commonly add special conditions to standard form contracts to allocate associated risks and responsibilities.
The Impact on Procurement of Materials
Shortages of construction materials have been very common due to COVID-19 (particularly timber, steel and plasterboard) and supply chains for specialised materials and equipment (particularly from overseas) are a common cause of delay on projects.
The construction industry has adapted to the supply chain delays with a range of strategies, including:
On some projects, employers are procuring key materials early and then free-issuing them to contractors.
The Impact on Labour
Worker absences on site due to COVID-19 have had a notable impact on productivity, and the infectiousness of COVID-19 can take a high number of workers off the site at the same time. Further, the effect of COVID-19 on international travel has made it more challenging to secure specialist labour for more complex projects.
The construction industry in New Zealand generally attempts to manage this risk by sourcing labour locally where possible and having COVID-19-specific health and safety policies in place.
The Impact on Costs
The inflationary pressures linked to the pandemic have been acute in the New Zealand construction market. A range of measures are used in New Zealand for allocating and managing this risk, including indexation of costs and early procurement of materials.
The Nature of Employers
The employer, also known as "the principal" in the NZS contracts, can be a wide range of persons including:
The Engineer as a Key Agent of Employers
The main NZS forms of contract includes the concept of "the engineer", which is similar to the engineer in the FIDIC series of contracts.
Under the NZS 3910:2013 and NZS 3916:2013 contracts, the engineer administrates the contract and has a dual role as an agent of the employer and a quasi-independent decision-maker. In the latter role, the engineer is expected to act fairly and impartially. Many of the roles of the employer referred to in this guide will actually be performed by the engineer (eg, issuing and assessing variations, confirming works are complete, etc).
General Rights and Responsibilities of Employers
Common rights
Common responsibilities
The Relationship Between Employers and Contractors
The employer and contractor will be the parties to the construction contract. The contractor is obliged to carry out the works specified in that contract, and the employer is obliged to pay for those works in accordance with the contract.
It is also common for the employer to require security from the contractor to ensure the due, proper and punctual performance of the contractor's obligations under the contract. This is commonly achieved through a contractor's performance bond or retentions from payments due to the contractor.
Once the contract is under way, to facilitate communication, the employer and contractor usually each have a single nominated representative to enable clear communication. For the employer, this is usually the engineer (or the engineer's representative).
The Relationship Between Employers and Subcontractors
See 2.3 The Subcontractors.
The Relationship Between Employers and Financiers
See 2.4 The Financiers.
The Nature of Contractors
There is significant variability in the size and nature of contractors commonly operating in New Zealand. Contractors range from large listed corporations (both local and overseas) to much smaller private companies. It is not uncommon for larger projects in New Zealand to involve overseas organisations (often in a joint venture with local entities).
Common Rights and Responsibilities of Contractors
Common rights
Common responsibilities
Contractors are not relieved from their responsibilities to the employer if they subcontract works to third parties.
The Relationship Between Contractors and Employers
See 2.1 The Employer.
The Relationship Between Contractors and Subcontractors
See 2.3 The Subcontractors.
The Relationship Between Contractors and Financiers
See 2.4 The Financiers.
The Nature of Subcontractors
Subcontractors can be a local, national or overseas entities. Subcontractors commonly specialise in specific trades.
Common Rights and Responsibilities of Subcontractors
The rights and responsibilities of subcontractors are typically akin to the rights and responsibilities between a contractor and the employer. See 2.2 The Contractor.
The Relationship Between Subcontractors and Employers
By default, due to privity of contract, the employer does not form a relationship with the contractor's subcontractors. However, through its contract with the contractor, the employer typically places some controls on subcontracting such as:
Moreover, it is not uncommon for employers to have limited rights in respect of certain subcontract works by virtue of:
The Relationship Between Subcontractors and Contractors
Subcontractors are engaged on a construction project through a subcontract with the contractor. It is common for a contractor to engage a variety of subcontractors, each with a specific trade, on a single project.
A subcontractor's scope of responsibility is generally limited to the work and risks outlined in its subcontract with the contractor. However, it is not uncommon for contractors to seek to pass risks in its contract with the employer down to the relevant subcontractor.
The Relationship Between Subcontractors and Financiers
See 2.4 The Financiers.
The Nature of Financiers and the Financing of Projects in New Zealand
Financiers of construction projects in New Zealand are typically local and foreign commercial banks, investment banks and institutional investors (such as pension funds). Multi-financier syndicates are common on larger projects.
Rights and Obligations of Financiers
Financiers are obliged to provide financing to the employer, but will not be party to the construction contract itself or otherwise have any direct obligations to the contractor (although they receive the benefit of undertakings from the contractor under a direct deed – see the relationship between financiers and contractors below).
In traditional construction financings, financiers take security over physical assets such as land and buildings, as well as over construction contracts and other material contracts such as sale agreements or leases. They may also receive the benefit of a guarantee from a parent company guaranteeing repayment of financing provided to its subsidiary, and/or take security over the shares in the employer held by its shareholder.
In limited recourse project financings, the security package may be similar; however, the financiers will have a significantly enhanced focus on the cash flows arising from the operation of the completed project. Accordingly, they will exercise a much higher degree of diligence in assessing and monitoring matters arising under the construction contract and related contracts (such as completion guarantees), given that the achievement of completion under the construction contract will unlock the cash flow.
The Relationship Between Financiers and Employers
The relationships between financiers and employers under construction projects are governed by the relevant finance and security documents. These will typically comprise a facility agreement, a general security agreement (providing for 'all assets' security over the employer), as well as one or more specific security agreements (for example, providing for an assignment by way of security of specific project contracts or for security over the shareholder's shares in the employer) and/or guarantees.
The Relationship Between Financiers and Contractors
On financed projects it is common for a direct deed to be agreed between the financier, the employer and the contractor.
A direct deed generally involves the contractor consenting to the security given to the financier over the construction contract, agreeing that certain insolvency action (such appointing a receiver) will not of itself trigger a contractor's right to terminate the construction contract, agreeing to give the financier additional cure periods to remedy a default of the employer under the construction contract that could otherwise lead to termination by the contractor, and pre-agreeing the basis on which the financier may sell the benefit of the construction contract and/or of the shares in the employer to a third party on enforcement of its security.
The Relationship Between Subcontractors and Financiers
It is uncommon for financiers and subcontractors to have a direct contractual relationship.
Sources and Descriptions of the Scope
The scope typically takes the form of:
Both requirements and specifications can also contain drawings setting out the locations, dimensions, forms and finishes required. Drawings are typically much more detailed in a construct-only contract.
The Scope in Tenders
The employer will typically initially set out its requirement for the works (commonly called the scope or specifications) in a closed or open tender process. It is not uncommon for the contractor and employer to negotiate that scope (eg, to reduce the price) before the contract is finalised and executed.
The Scope in Contracts
Once the contract is executed, the scope is generally fixed and can only be modified thereafter if, and to the extent, permitted by the terms of the contract itself (see 3.2 Variations).
Instructing Variations
The scope of an instructed variation is typically at the sole discretion of the employer, and in NZS contracts a variation is typically instructed via the engineer. In New Zealand, contracts typically permit the employer/engineer to:
Some events/circumstances are also commonly variations even though they do not arise from an instruction from the employer/engineer, eg, unforeseen ground conditions and archaeological discoveries.
Valuing Variations
The process for valuing variations differs across contracts. In New Zealand, particularly in NZS contracts, valuation is established by one of the following methods (in descending order of precedence):
Where rates do not include overheads and margins, or the variation is valued on a net cost basis, allowances for overheads and margins are usually added.
In New Zealand, the two most common frameworks for allocating design responsibilities and risk are the following.
Construct Only
The contractor is responsible for its methodology of construction based on the design, but not for errors or omissions in the design itself.
Design and Construct
The contractor is responsible for both the design and the construction of the works (if the owner has a pre-existing design, it may be novated to the contractor).
The employer's role in the construction itself is generally limited to providing site access for the contractor and its subcontractors. However, the employer may be obliged to provide supplementary information/design clarification when requested by the contractor.
The contractor generally has the autonomy and primary obligation to:
Subcontractors are managed by the contractor, and have a similar role to the contractor in respect of their subcontracted works.
The employer is typically responsible for making the site available to the contractor by a particular date for the purposes of performing the works.
In respect of the geotechnical site conditions, responsibility and risk can vary significantly by contract. Commonly, the employer will bear the risks of adverse conditions unless:
Contamination
Pre-existing contamination is typically the employer's responsibility, whereas the contractor is typically responsible for ensuring that it does not contaminate or pollute the site in the course of construction.
Pollution and contamination is governed by the Resource Management Act and often local council guidelines.
Archaeological Finds
Archaeological discoveries, and any delays and additional costs caused by such discoveries, are usually the employer's responsibility.
Archaeological finds on a construction site are governed by the Heritage New Zealand Pouhere Taonga Act 2014, which requires that no person may modify or destroy a site if that person knows, or ought reasonably to have suspected, that the site is an archaeological site.
Common Permits
Responsibility for Permits
Arrangements for permits typically vary by contract. Generally:
Most construction contracts exclude general maintenance obligations after completion. These become the employer's responsibility.
Typically, the employer will enter either self-perform maintenance works or enter into separate maintenance service agreements with third parties for the proper operation and maintenance of the works. The NZS3917:2013 fixed-term contract is available for such maintenance services.
For defects in construction works arising after practical completion, see 3.11 Defects and Defects Liability Period.
Finance and maintenance primarily sit outside the construction contract between the employer and the contractor. See 2.4 The Financiers and 3.7 Maintenance.
Some projects require key materials or equipment to be tested to ensure that they meet contractual or regulatory requirements.
The processes vary by contract. The contractor will typically give the employer notice of the date when it will be ready for such tests to be carried out. The contractor will commonly carry out the tests, or arrange for the tests to be performed by specialists, with the employer having the right to attend (or to have an agent attend) such tests.
There are numerous potential testing types and stages. Common tests include:
Completion/Taking Over
Most standard forms set out a process for verifying/delineating when works are completed/taken over. In some contracts this can be a multi-stage process, eg:
For construction contracts, the employer (or, more commonly, its engineer) will typically inspect the works and issue a practical completion certificate, and later a final completion certificate, certifying the works meet the requirements of the contract.
However, there are also some actions (eg taking possession and using the works before practical completion) that can result in the employer being deemed to have taken over the works.
Delivery
The term delivery is typically used for materials or equipment, and is often linked to obligations to make payment and the transfer/allocation of risk or title.
In New Zealand, the point of delivery will usually be expressly stated in the contract. The International Chamber of Commerce's Incoterms rules are not mandatory, but are commonly referred to for international deliveries.
Most construction contracts have a limited period after the works are completed (which can range from a few months to a couple of years) within which the contractor must remedy any snags/defects (commonly called a defects notification period, or DNP). In addition, the employer will often require various standalone warranties for defects arising after the DNP.
Common standalone warranties include key materials/equipment and weathertightness. The NZS forms of contract include standard form warranties as a schedule to the main terms.
Defect Notification Periods
Typically, if a defect or fault emerges during a defect notification period as a result of defective workmanship or materials, the contractor is obliged to remedy the defect or fault.
If the contractor does not remedy the works within a reasonable time, the employer can often engage third parties to remedy the works and then recover the cost of doing so from the contractor.
It is also common for employers to retain some of the contract price as a retention until the end of the defect notification period, to incentivise the contractor to return to fix such defects and thereby ensure the payment of the retentions.
Statutory Warranties
Under the Building Act 2004, residential building work is covered by a ten-year warranty. Parties may not contract out of this warranty.
Cost Structures
The most common structures used to price construction projects are:
Alliances and other forms of collaborative contracting are increasingly used on major projects.
Payment Structures
In New Zealand, it is common for project payments to be based on either:
Advance Payments
Advance payments are common in New Zealand for long lead items, and have become more common recently as a means of locking in costs and reducing the risk of delays due to COVID-19.
If materials are to be paid for before they arrive on site, separate agreements for offsite materials are often entered into to allocate the relevant risks and obligations. The NZS forms of contract include standard form offsite material agreements as a schedule to the main terms.
Employers also commonly protect their interests in high-value advance payments by way of advance payment bonds.
Progress Payments
Typically, at regular intervals, the contractor submits a payment claim. The employer will then assess the claim and issue a payment schedule of amounts that it considers to be due.
Late Payments
Construction contracts in New Zealand typically include interest on late payments.
The Construction Contracts Act 2002 has default payment structures intended to ensure regular cash flow throughout the industry. If a qualifying payment claim/invoice (see 4.3 Invoicing) is not appropriately disputed in a payment schedule and is then late/unpaid, the act enables a contractor to:
Requirements for Tax Invoices
In New Zealand, an invoice will typically include:
Recommended Requirements for Construction Invoices
To benefit from the Construction Contracts Act (see 4.3 Payment), a payment claim/invoice should:
Invoices issued after payment claims are typically a formality to reflect the outcome of the payment claim and payment schedule process.
The Role of, and Responsibility for, Construction Programmes
In New Zealand, a programme is usually prepared by the contractor at the outset of a project and it is often integral to setting up a project for success. The programme is often reviewed by the employer, who may provide comments/input, but good programming is ultimately the contractor's responsibility.
Contracts commonly require the contractor to report against, and update, the programme regularly over the course of a project.
Common Programme Requirements
Standard contractual requirements for a programme are that it should set out:
If a delay occurs, most contracts in New Zealand include a process along the following lines:
There is an expectation in New Zealand that contractors will take reasonable measures to avoid potential delay events, and to mitigate delays if such events occur. In standard form contracts, failure to give notice can affect the contractor's eligibility for extensions of time and variations if it deprives the employer of the opportunity to avoid or mitigate the delay.
Contractor Delays
If the contractor is responsible for the delay, then contracts will commonly provide that the contractor:
Employer Delays
If the employer is responsible for the delay, then contracts will commonly provide that the employer will:
Contractors usually issue notices for extensions of time to the employer/engineer in writing.
Contractors are typically required to set out the basis for an extension of time claim under the contract. Common grounds for an extension of time claim include:
In New Zealand, force majeure only applies if it is expressly included in the contract.
Force majeure clauses are not included in most New Zealand construction contracts as standard. However:
Relief for unforeseen circumstances is generally only available if it is included in the contract (albeit New Zealand recognises the common law concept of frustration, which can apply in some instances of unforeseen circumstances). Frustration is grounds for termination under the NZS 3910:2013 and NZS 3916:2013 contracts.
In standard form contracts in New Zealand, a contractor is commonly entitled to additional time for unforeseen circumstances but not necessarily additional costs.
Warranties under the Building Act 2004 cannot be contracted out of for residential properties.
On policy grounds, a person cannot exclude liability for their own fraud.
The concepts of wilful misconduct and gross negligence are not well-established in the New Zealand courts. However, where contracts include limitations on liability (see 6.3 Limitation of Liability), such clauses often seek to ensure that any limitation of liability does not apply if the contractor engages in wilful misconduct or gross negligence.
Consumer Contracts
In consumer contracts in New Zealand, limitations of liability are restricted by the Consumer Guarantees Act 1993. For example, a contractor cannot limit its liability for completing construction with reasonable skill and care, so that it is fit for purpose, and on time or within a reasonable timeframe.
Commercial Contracts
In CBL Insurance Ltd (Liq) v Harris [2021] NZHC 1393, the High Court confirmed that clear limits of liability are enforceable in commercial contracts in New Zealand.
Limitations of liability are not included in New Zealand's most common standard form contracts, but it is not uncommon for parties to add such clauses.
Parties are generally free to negotiate indemnities subject to policy restrictions – eg, not indemnifying certain court issued fines and penalties. Standard form contracts in New Zealand typically include indemnities:
It is not uncommon for parties to agree further indemnities (to the extent permitted by law) for:
There are no mandatory guarantees in New Zealand. However, there are several forms of performance guarantee that are common in the New Zealand market.
Bonds
Standard form contracts in New Zealand anticipate performance bonds. These may be provided by the principal to the contractor, or by the contractor to the principal.
Parent Company Guarantees
If the contractor is a subsidiary and/or has limited assets, the employer may require (and financiers may expect) performance to be assured by way of a guarantee from a parent company.
In the NZS standard forms of contract, there are four types of insurances that are commonly taken out by the parties:
However, it is not uncommon for other insurances, such as marine cargo insurance, to be taken out where the specific project involves relevant risks.
Under most contracts in New Zealand, the insolvency of a party typically permits the other party to terminate the contract. The insolvency of the contractor commonly also permits the employer to resume possession of the site.
Risk-sharing arrangements are not particularly common in New Zealand, and are most often found in alliance agreements or target cost arrangements (see 4.1 Contract Price).
The orthodox approach regarding risk in New Zealand is to allocate the risk to the party who is best placed to control that risk, or for a party to accept additional risk in return for a price premium (if accepted by the contractor) or reduction (if accepted by the employer).
It is not uncommon for employers to require the contractor to:
The standard NZS construction contract prohibits a contractor from subcontracting the whole or substantially the whole of the works. Subcontracting generally requires the employer's consent.
Subcontracting does not relieve the contractor from any liability or contractual obligations owed to the employer under the contract.
Typically the employer and the contractor will each retain their intellectual property rights, but grant licences to the other to the extent necessary for the project. Rights over new intellectual property that may result from a project are typically negotiated and vary significantly – a common approach is shared ownership with cross-licences.
It is not uncommon for parties to agree indemnities for infringement of third-party intellectual property rights.
Contract law in New Zealand recognises general damages for breach of contract. Sufficiently serious breaches of contract may also entitle a party to terminate the contract.
Common Employer Remedies
Common Contractor Remedies
See 6.1 Exclusion of Liability, 6.3 Limitation of Liability, 9.3 Sole Remedy Clauses and 9.4 Excluded Damages.
It is common for parties to limit the duration of some liabilities, for example liability under consultancy contacts is typically limited to six years.
Sole remedy clauses, also referred as exclusive remedy clauses, are not included in the standard NZS construction contracts but are enforceable in commercial contracts. However, these are not widely used in New Zealand.
Where a contract provides for delay liquidated damages, that will typically be considered the sole remedy for delay.
It is not uncommon for commercial parties in New Zealand to exclude liability for:
Retentions
Retentions are permitted and common in New Zealand construction contracts. Employers are required to hold retention monies on trust for the contractor under the Construction Contracts Act. Further requirements, such as holding retentions in a separate account, are anticipated in the near future.
Suspension Rights
Contractors have statutory suspension rights for non-payment but, under the NZS forms of contract, are typically not permitted to suspend works due to a dispute.
Courts
In New Zealand there are four tiers of court that may hear construction disputes (in descending order):
Adjudication
In New Zealand, parties may not contract out of the adjudication process, which is set out in the Construction Contracts Act.
Adjudication is a relatively swift but interim dispute resolution process that takes place entirely by way of written submissions (there are no hearings). Adjudication decisions are binding and any awards must be paid within two working days of award. Notwithstanding the obligation to pay, parties may then proceed to litigation or arbitration for final determination of the dispute.
Adjudications are determined by a single adjudicator from a recognised institution.
Recognised Institutions
In New Zealand, there are several institutions recognised as competent to appoint persons to hear construction disputes as adjudicators or arbitrators. These include:
Private and alternative dispute resolution options recognised in New Zealand include:
Level 3
Australis Nathan Building
37 Galway Street
Britomart
Auckland 1010
New Zealand
+64 9 338 8300
+64 9 337 1115
lawyers@al.nz www.al.nz