In Denmark, there are no laws specifically governing the contractual relationship between an employer and a contractor. Instead, there are several standard contracts that have the status of agreed documents and which virtually all larger construction contracts are based on, see 1.2 Standard Contracts.
With regard to statutory requirements related to buildings and constructions, this is mainly governed in the Danish Building Act and the appertaining ministerial orders.
Furthermore, there is the Danish Contracts Act, which regulates, inter alia, when and how a contract is agreed and binding. It also contains certain principles of interpretation.
As mentioned in 1.1 Governing Law, larger construction contracts are usually based on a suite of standard contracts governing the relationship between the employer-contractor, employer-designer, contractor-subcontractor and contractor-designer. However, the use of standard contracts is not mandatory.
Construction contracts in Denmark are rarely based on FIDIC, NEC3 or the like, due to the availability of the aforementioned standard documents, which are somewhat comparable to the standard documents used in other parts of Scandinavia (Sweden and Norway).
The AB Standards
The Danish standard documents are agreed documents, meaning that they have been prepared based on, inter alia, negotiations between opposing interest groups. A committee appointed by the Danish Minister for Climate, Energy and Building (and containing representatives from the interest groups) has formulated three standard contracts (the “AB Standards”) for use in construction in Denmark:
The AB Standards set out the parties’ contractual rights, obligations and responsibilities and are used alongside the parties’ construction contract, which is often brief.
Though the AB Standards are, to some extent, a codification of generally applicable Danish legal principles, the AB Standards only apply if the parties have agreed thereto.
Currently, the COVID-19 pandemic no longer heavily affects the Danish construction industry and, despite the pandemic, activity was on the rise through 2021. However, several projects (including major infrastructure projects) suffer from the aftermath of the health crisis, including consequential issues related to global supply lines. Further, several projects have been delayed and costs increased.
Restrictions and Protective Measures
The COVID-19 pandemic entailed certain restrictions and protective measures, which have of course burdened those working within the industry and affected projects in terms of prolonged construction time and increased costs.
All COVID-19-related restrictions in Denmark are now lifted and the disease is no longer classified as being a critical threat to society.
As part of the general obligations under the Danish Working Environment Act, for example, the employer (as defined from an employment law perspective) has an obligation to ensure that work is planned, organised and carried out in a way that ensures health and safety. These obligations must continuously be viewed in light of and take into account that the spread of COVID-19, like other diseases, must be prevented.
Despite the current status of the disease, several employers continue to have COVID-19 policies in place.
In Denmark, the entities acting as employers in construction projects vary greatly. Common entities are the Danish state, regional authorities and municipalities, as well as co-operative housing societies. Similarly, the private sector plays a large role, and is responsible for around two-thirds of the total investments.
Under a construction contract, the rights and obligations of the employer depend, of course, on the specific contract entered. However, generally, during the contract conclusion period, the employer:
During the construction phase, the employer has a number of management and control obligations and rights towards the contractor, as detailed in the AB Standards.
Companies that typically act as contractors may be divided into larger construction groups, specialising in design-and-build contracts, and specialised contractors who focus on certain fields of construction and therefore often act as subcontractors to design-and-build contractors.
Generally speaking, the contractor is responsible for the planning and execution of the works and has, unless otherwise agreed, freedom of choice as to how the works are to be performed. Besides performing the works, a contractor must usually provide security for fulfilment of its duties towards the employer, take out liability insurance, deliver materials, prepare and update working schedules, etc.
Subcontractors are typically companies with specialist knowledge in a specific area; typical examples are the so-called technical (sub)contractors, specialising in areas such as ventilation, electricity, and plumbing and heating.
Contractually speaking, a design-and-build contractor is – vis-à-vis its subcontractors – considered an employer in Denmark. The general rights and obligations of the subcontractors are therefore comparable with the rights and obligations of the contractor towards the employer.
Construction projects in Denmark are most commonly financed by private banks, pension funds and public entities.
The financiers are not a party to the construction contract but have an independent contractual relationship with the relevant party. As such, the financiers have no direct rights or obligations under the construction contract, besides those following from guarantees issued by the financiers.
Any control or rights would therefore have to be agreed upon in the contract between the financier and the debtor. As an example, the financier may have an interest in novating the construction contract if the employer goes bankrupt. Such right to novate an agreement must generally be agreed upon in advance under the construction contract between the employer and the contractor.
Given the freedom of contract, the scope of work can be determined in any way the contractual parties agree to. Essentially, the scope of work is determined by the employer in the tender documents, either in the form of certain functional requirements to be achieved or in the form of a more detailed set of specifications, depending on the type of contract. Such scope of work is subject to agreement (potentially after negotiations) with the contractor(s).
When the contract is concluded, the scope of work is (in theory) set, and any additional work or changes thereto may entail that the contractor is entitled to additional payment and time.
Whereas the requirements regarding the work to be performed tend to be categorised as functional or performance requirements in design-and-build contracts (ABT 18), the requirements regarding the work tend to be more specified in other construction contracts (AB 18).
Employer's Rights
In accordance with the AB Standards, the employer has a right to order variations to the works when such variations are naturally linked to the services agreed upon.
An example of a variation could be that the contractor must supply a service in addition to, or instead of, the originally agreed service. However, a change in the nature, quality, type or execution of a service may also be considered a variation.
The employer’s right to order variations is not unlimited. As stated above, it is a requirement that the variation is naturally linked to the services agreed.
Rights of the Contractor
It is also worth noting that – to balance the contractor’s interest – the contractor has a right to carry out (and be paid for) variations demanded by the employer, unless the employer proves that there are special reasons for having another contractor perform the work. Such special reason may, inter alia, be that the contractor does not have the necessary technical knowledge to perform the variation or that the payment requested by the contractor is unreasonable. As such, the employer cannot simply engage a new contractor to perform work that is naturally linked to the works that the already-engaged contractor has performed on a project.
Determining the Price
With regards to determining the price of the variation, this depends on the specific AB Standard entered into, but pricing is commonly either done based on unit rates agreed in the contract or on an account basis. With regard to the latter, the contractor may claim what is reasonable, and it is up to the employer to prove that the claimed price is unreasonable.
The responsibilities regarding the design process between the employer, the designer, and the contractor depend on the parties’ agreement and may be construed with many nuances and hybrids. However, some general starting points can be discerned from the AB Standards.
AB 18 – Contractor Only Carries Out the Building and Construction Work
If AB 18 is agreed, the employer and the contractor have – as a starting point – agreed that the contractor “only” carries out the building and construction works, and that the employer is responsible for the design (drawings, descriptions, etc).
In such cases, the employer bears the full responsibility for the design, and the contractor is only to carry out design work if this has been agreed.
With an AB 18 set-up, the employer will usually enter a contract with a designer/consultant to carry out the designs on behalf of the employer – such contract is usually based on an ABR 18, see 1.2 Standard Contracts. The designer/consultant will then be responsible for the design in the contractual relationship between the employer and the designer/consultant.
ABT 18 – Contractor Carries Out the Building and Construction Work and Design (Design and Build)
The employer and contractor can agree that the contractor carries out the building and construction works and supplies the design. ABT 18 is relevant for this type of agreement, see 1.2 Standard Contracts.
In such cases, the contractor bears the full responsibility for the design in the relationship between the employer and the contractor. However, if the employer has proposed a specific type of design in the tender documents and the design is applied, then the contractor may not be responsible for this design.
The contractor will, in such instances, often enter a contract with a designer/consultant to carry out the design (based on ABR 18), and the designer/consultant is therefore responsible for these designs in the relationship between the contractor and the designer/consultant.
The division of responsibilities in the construction process between the employer and the contractor(s) depends on which AB Standard has been agreed, namely AB 18 or ABT 18.
To give an example, some of the employer’s and contractor’s main responsibilities during the construction process (after the design phase) in an AB 18 set-up may be described as the following.
Employer's Responsibilities
The employer is responsible for:
Contractor's Responsibilities
The contractor(s) is responsible for the work performed, namely, that the work is performed in accordance with the contract (the design, possible requirements, etc) but also more generally that the work is done in accordance with good professional practice. If the work is not performed in accordance with the contract or good professional practice, that work is considered defective.
The contractor is, as a starting point, also responsible for preparing a work schedule (based on the master programme), which states the sequence of the individual elements of the contractor’s work, including assessing compliance with this schedule on an ongoing basis. The contractor is further responsible for quality assurance of its services.
The above-described division of responsibilities may, however, be amended as the parties see fit, and the possible division of work is therefore completely up to the parties concerned.
Information About Obstacles at the Construction Site
Regarding the status of the construction site, the tender document must include information about surveys and studies made concerning groundwater and soil conditions, pollution, pipes, cables, hazardous substances and materials, as well as any other obstacles. This follows from both AB 18 and ABT 18. Thus, the employer is responsible for inspecting the construction site, unless otherwise stated in the contract between the employer and the contractor.
If the contractor finds that the work cannot be performed in accordance with the contract due to obstacles, the contractor must notify the employer immediately and await instructions.
Public Enforcement Notices or Prohibitions
It is also worth noting that the authorities are entitled to issue public enforcement notices or prohibitions. This is the case if something at the construction site does not fulfil, for example, regulatory requirements for pollution, or if archaeological finds are discovered at the site. The employer bears the risk for such notices or prohibitions unless they have been issued as a result of the contractor’s actions.
Most construction projects require a building permit, which is issued by the local municipality upon the employer’s application, before the construction process begins. The permit is only given if the construction project is in accordance with Danish building regulations and the local development plan, if applicable.
Upon completion of the construction project, the employer must apply for an occupancy permit before using the new building. The occupancy permit is given by the municipality after receiving all the relevant documents, including a declaration stating that the construction work has been carried out in accordance with the building permit and the building regulations.
The building permit and the occupation permit are governed by mandatory law (Danish Building Act).
The contractor bears the risk of damage to, or loss of, works and materials until the work has been handed over to the employer – see 1.2 Standard Contracts, AB 18 and ABT 18.
Contractor's Responsibilities
The contractor is, therefore, also responsible for maintenance of the works during the construction. While the contractor obviously has an interest in taking care of the works during the construction, it is essentially up to the contractor how this obligation is fulfilled.
Employer's Responsibilities
When the work has been handed over, the employer is responsible for damage to and loss of works and materials, as well as maintenance. During the construction process, the employer is also responsible for damage to or loss of works if the damage or loss is due to circumstances relating to the employer. If the work or part thereof is taken into use before the handover, the employer is also responsible for any loss or damage to the work occurring thereafter.
Other functions in the construction process such as operation, finance or transfer are usually not instructed by the employer to the contractor or third parties. Exceptions do occur, however – for example, in large infrastructure projects.
Before providing a few notes on the tests for completion of works in Denmark, it is important to note that the relevant time for evaluating whether a work is defective is the time of handover.
The quality of the works will therefore be assessed during the handover meeting, but actual tests are usually not part of the ordinary handover meeting.
This must be viewed in light of the fact that construction contracts often include provisions requiring the contractor to perform certain quality assurance of the works, including the design, as well as provisions on samples or tests to be taken prior to handover. The result of such tests will therefore be part of the contractor’s quality assurance documentation, submitted to the employer on an ongoing basis prior to handover.
As a new rule in the AB Standards (revised in 2018), the parties must – prior to the actual handover of the works – conduct a pre-handover review.
Pre-handover Review
The purpose of conducting a pre-handover review is to support a continuous inspection for defects and to align the parties’ expectations.
Prior to handover of the works, the employer must summon the parties to attend a review of the works (all or sections thereof) in reasonable time before the agreed handover date. At the pre-handover review, the employer prepares a protocol stating all matters identified, and any remarks made by the contractor. If the identified matters are considered defects by the employer (and the contractor), the contractor will agree to rectify the identified defects. The fact that a matter has not been identified by the employer at the pre-handover review does not preclude the employer from later raising the matter as a defect.
The Actual Handover Meeting
Immediately before the completion of the works, the contractor must give the employer a notice of completion, after which the employer will summon the contractor for the actual handover meeting. Once the handover meeting has been held, the works are considered handed over to the employer, unless material defects are identified at the meeting. Material defects will particularly be matters preventing the employer’s use of the works to a significant extent.
At the handover meeting, the employer prepares a handover protocol in which the defects and other matters identified are stated. In addition, the parties agree on the methods and deadlines for the rectification of the defects. The handover protocol will state whether the works are considered handed over.
Defects Liability Period in Accordance With the AB Standards
Inspection of the works is made at the handover, one year after the handover and again, five years after the handover. The purpose of these inspections is to enable the parties to identify any defects together.
An absolute deadline to present claims regarding defects detected is also regulated in the AB Standards, ie, the employer’s claims must be submitted no later than five years after handover of the works, after which the contractor’s liability for defects generally ceases. Exceptions may be made where the contractor has given a guarantee, the quality assurance process has materially failed, or the contractor has acted in a manner that is grossly negligent.
Danish Statute of Limitations Act
In Denmark, it follows from the Danish Statute of Limitations Act that a claim becomes statute-barred three years after the claimant became or should have become aware of the circumstances giving rise to the claim. This applies in parallel with the rules in the AB Standards.
The limitation period may be suspended by, for example, mutual agreement, or by taking legal action to pursue the claim.
Acquiescence Resulting in the Forfeiture of Rights and Failure to Notify of Defects
Furthermore, according to Danish case law, the employer may lose an otherwise entitled claim in respect of defects against the contractor if the employer, for example, fails to notify the contractor within a reasonable period of time after the defects were or should have been discovered (even though the claim is presented within the five-year period). Likewise, the employer may lose its claim if the employer’s behaviour and conduct give the contractor a reasonable expectation that the claim does not exist or has been forfeited. These principles apply in parallel to the AB Standards and the Danish Statute of Limitations Act.
In Denmark, the contract price can either be a fixed price, on account or a combination of these. The most common way of establishing the contract price is by using a fixed price. However, this will depend on the parties’ agreement.
In general, the contract price includes all services and materials necessary for the contractor’s completion of the scope of works. The contractor’s offer, including the price, is based on the employer’s tender provided to the contractor as a basis for the preparation of the offer. In this way, it is essentially up to the contractor to establish the contract price – assuming, of course, that the employer accepts the offer.
In relation to payments, the contractor is entitled to receive payment twice a month for any works performed and materials delivered to the construction site, in accordance with the AB Standards. However, the parties may instead agree that payment is to be made in accordance with a payment schedule, stipulating the dates or milestones at which a certain percentage of the contract sum falls due for payment, provided that the progress of the works at that time is as planned.
In cases of late or non-payment, the contractor has a number of options.
The contractor is entitled to claim interest in accordance with the agreement or, if nothing has been agreed, the Danish Interest Act.
The contractor is also entitled to stop the construction works if the employer without due cause refuses to pay the amount due by the final date for payment. To be entitled to stop the work, the contractor must first submit a written notice to the employer with a short deadline for payment. The condition thereafter is that the work will be resumed when the payment has been made by the employer. However, stopping the work may include a considerable risk, as the contractor may be liable for the employer’s losses if it turns out that the contractor was not entitled to the payment claimed, and on which basis the works were stopped.
Ultimately, the contractor may be entitled to terminate the construction contract if the employer fails to fulfil its key obligation, namely payment to the contractor. This depends, however, on the circumstances.
There are no mandatory means of invoicing in Denmark, as this depends on the agreement between the parties. Typically, the parties agree on certain procedures and requirements in respect of invoicing.
Often, the parties agree that the contractor must forward a “draft invoice” to the employer for approval before submitting the actual invoice (to avoid issuing credit notes, etc).
Generally, however, no specific rules on this apply – either by law or in the AB Standards.
In accordance with the AB Standards, the tender documents must include a master programme specifying, among other things, the start and end date of the work and interim deadlines, if any. See also 3.4 Construction.
When the construction contract is entered, the contractor must prepare a working/design schedule and execution schedule that meet the deadlines set out in the agreed master programme.
If it seems likely that the schedules will not be adhered to, they must be updated stating to what extent an extension of time is requested or accepted, and whether the delay concerns a deadline associated with liquidated damages.
Certain milestones are often included in the master programme, and it is not unusual that if such interim milestones are exceeded by the contractor, this will entitle the employer to claim liquidated damages. The liquidated damages must, however, be specifically agreed and the deadline must have been set to ensure the completion of an activity crucial to the construction process or other material issues.
In the event of delays, the party that becomes aware that there will be a delay must notify the other party as soon as possible. Furthermore, the parties must endeavour to avoid or reduce delays by taking such measures as may reasonably be required.
Delays may entitle either the contractor or the employer, or both, to an extension of time (see also 5.4 Extension of Time). In such cases, the party concerned must notify the other party in writing of the required time extension and the reason for such extension, and the other party must respond to this.
If a contractor is delayed and not entitled to an extension of time, this constitutes an actionable wrong.
In the event of a delay where the contractor is not entitled to an extension of time, the employer is, as a starting point, entitled to claim its losses covered by the contractor.
However, most construction contracts contain an agreement on liquidated damages if the milestone date is exceeded, which is often agreed as a daily penalty fixed as pro mille of the contract sum (usually in the range of 0.5–2‰).
If liquidated damages have been agreed, the employer is not entitled to claim additional damages as a result of the delay in question – including where the employer’s loss exceeds the liquidated damages. In other words, the liquidated damages replace the employer’s right to claim its losses covered by the contractor in the event of the contractor’s delay. Conversely, the employer does not have to prove a loss if liquidated damages have been agreed.
As such, there are pros and cons to both types of sanctions (loss covered or liquidated damages).
If the agreement is deemed unreasonable, however, a Danish court or an arbitral tribunal can revise the agreed rate of liquidated damages.
In accordance with the AB Standards, the contractor is entitled to an extension of time if the execution of the works is delayed as a result of:
The contractor must, as soon as possible, notify the employer in writing of the required time extension and the reason for such extension.
In the AB Standards, the term "force majeure" covers exceptional external events beyond the control or responsibility of the parties. This would usually include war, riots, acts of terrorism and acts of God.
The term force majeure may differ in Danish construction law, depending on the situation. As such, force majeure is considered to have a wider scope when referring to the contractor’s entitlement to an extension of time compared to when considering the contractor’s risk related to damage to, or loss of, works and materials.
With regard to the contractor’s entitlement to claim extension of time, matters such as fire, strikes, lockouts, blockage and vandalism are usually considered force majeure.
In relation to the COVID-19 pandemic, this may have been a force majeure circumstance in Denmark. However, this will depend on the specific circumstances and, at the time of writing, no case law has been published on the subject matter.
The war in Ukraine may, in and of itself, constitute a force majeure circumstance allowing for easing of obligations. However, in order to receive compensation, which under the AB Standards is generally for time only, several criteria must be met, inter alia that the effect must be unforeseeable, and that the parties must fulfil quite strict duties to mitigate the effects, for instance by seeking out other suppliers, materials, etc.
It is not unusual for the term force majeure to be specifically defined in the construction contract, which may prevent subsequent disputes regarding the interpretation of this term.
Unforeseen circumstances may qualify as force majeure if the circumstances, as mentioned, are exceptional and beyond the control of the parties. However, if the unforeseen circumstances cannot be qualified as force majeure, the question arises as to who is liable for the unforeseen circumstances.
If unforeseen circumstances – despite the performance of preliminary studies as mentioned in 3.5 Site Access – lead to public enforcement notices or prohibitions that make it impossible or unreasonably burdensome for the employer to continue with the contract, the employer is entitled to cancel the contract with the contractor. In such case, the contractor is entitled to claim its losses covered by the employer (except lost profit related to non-completion of the remaining works).
Such scenarios are, luckily, rarely seen, and the most common result of unforeseen circumstances is that the contractor receives an extension of time and additional payment to overcome the unforeseen obstacles, etc.
As a general rule, liability may be limited by the agreement between the parties within construction contracts. In Danish construction contracts, this mainly finds expression in agreeing to a specific cap for which a party can be liable.
For instance, in ABR 18 (the employer/contractor–consultant standard agreement), the consultant’s maximum liability for damages is limited to twice the agreed consultancy fee, but no less than DKK2.5 million – provided that no project liability insurance has been taken out.
However, as an exception to the general rule of freedom of contract, it should be noted that an exclusion of liability may not apply if the party in question has acted with gross negligence or wilful misconduct or if the party has materially breached its core obligations.
Wilful misconduct and gross negligence are known legal concepts in Denmark – also in relation to a construction contract. Besides in relation to a limitation of liability as described in 6.1 Exclusion of Liability, these terms are also relevant in relation to the AB Standards and, more generally, compensation.
AB Standards
As an example, even if the five-year absolute deadline for submission of a claim related to defects has been exceeded (as described in 3.11 Defects and Defects Liability Period), the employer’s claims for defects that are a result of the contractor acting with gross negligence or wilful misconduct are not limited by this period.
Another example is the employer’s relationship to its contractor’s subcontractors. As a part of the AB Standards, the employer waives any claim for non-contractual damages against its contractor’s subcontractors in respect of matters covered by a direct claim for defects. This, however, does not apply if the direct claim for defects against the subcontractor has been caused by an intentional or grossly negligent act on the part of the subcontractor.
Compensation
Furthermore, negligence is relevant for establishing a basis for liability in relation to compensation. However, in Denmark, ordinary negligence is sufficient to establish this basis of liability.
As described in 6.1 Exclusion of Liability, it is – as a clear starting point – possible to limit one’s liability.
In Danish construction contracts, this is usually done in the contracts between an employer/contractor and a consultant. Furthermore, a contractor’s liability may also be limited to a certain maximum amount.
Since the AB Standards divide the responsibilities and risks between the parties in a thorough and balanced way, specific indemnity clauses are generally not used to limit risk in relation to construction projects in Denmark.
In accordance with AB 18 and ABT 18, both the contractor and the employer must provide a performance bond as security for the performance of their obligations. This does not apply to the employer if the employer is a social housing organisation or a public employer.
A performance bond must, unless otherwise agreed, be in the form of an adequate bank guarantee, fidelity insurance or some other adequate type of security. Parent company guarantees do not meet this requirement, but it may be agreed between the parties that such a guarantee is sufficient.
Until handover has taken place, the contractor’s performance bond must correspond to 15% of the contract sum exclusive of VAT. After handover, the performance bond is reduced to 10%. The performance bond is further reduced from 10% to 2% one year after handover and ceases altogether five years after handover, unless the employer has submitted a prior written notice of defects. In such a case, the bond is reduced when the defects have been rectified.
The employer’s performance bond must correspond to three months’ average payments – but not less than 10% – of the contract sum exclusive of VAT. The performance bond will cease once the contractor has submitted the final account and has no outstanding claims.
Both the employer and the contractor can request payment under the performance bond. Such request must be made in writing and notified simultaneously to the other party and the guarantor, specifying the amount claimed. The amount claimed is payable to the contractor within ten working days after receipt of the notification unless the relevant other party has filed a request with the Danish Building and Construction Arbitration Board prior to this, asking the board to issue a decision on the security provided under the performance bond, in particular, with a view to determining whether the payment claim is justified.
Some insurances are mandatory when entering a construction contract and carrying out construction work in Denmark. The insurances must be taken out by either the employer or the contractor.
Insurances Taken Out by the Employer
The employer is obliged to take out and pay for fire and storm insurance according to AB 18 and ABT 18.
Furthermore, the employer must take out building damage insurance if a building is mainly used for residency: see the Danish Building Act. This is unless the building is intended to be rented out.
As an optional insurance, the parties can agree on all-risk insurance, which is commonly agreed for large buildings or civil engineering work contracts.
Insurances Taken Out by the Contractor
The contractor is obliged to take out professional and product liability insurance. This is insurance that covers damages to employer’s or a third-party’s person or property. However, the insurance does not cover damages to objects where the damage is caused during performance of repairs, installing, mounting or, in other ways, reworks, and where the insured has accepted these works.
The provisions regarding bankruptcy and insolvency are similar in the various AB Standards and apply if a party is declared bankrupt, subject to reconstruction proceedings or if the party’s financial situation in general is such that it must be assumed that the party is unable to perform its obligations under the construction contract.
If one of these scenarios occurs (eg, bankruptcy), the other party is entitled to terminate the construction contract.
Prior to the actual termination, however, the party must give a written notification to the bankruptcy estate, and the estate must determine whether it wishes to become a party to the contract. This follows from the Danish Bankruptcy Act.
It is worth noting that the bankruptcy estate must give notice of this without undue delay, and the bankruptcy estate will seldom enter into a construction contract.
In the situation where a party is subject to reconstruction proceedings or, due to its financial situation, is assumed to be unable to perform the construction contract, that party may avoid a termination by immediately providing adequate security for the performance of the contract.
In Denmark, there is nothing to prevent the parties from agreeing to share a certain risk. However, such risk sharing is not a common practice in construction contracts.
In recent years, there has been an increase in so-called labour clauses. Such clauses usually oblige those working on a construction project to ensure that the workers employed receive wages, special allowances and enjoy working conditions that are no less favourable than those established for work of the same character under a collective agreement entered into by most representative organisations of workers and employers in Denmark in the industry concerned.
Such clauses are mandatory when one of the parties is a public entity, but these clauses are becoming more and more common for private entities as well.
In accordance with AB Standards, the contractor or consultant may subcontract the execution of the works or the design to subcontractors or subconsultants if it is customary or natural for the works/design to be executed by a subcontractor.
However, in larger construction contracts, it is often agreed that all or specified parts of the works are to be executed by the contractor or that the employer must pre-approve subcontractors.
Intellectual property is not regulated in the AB Standards. The general starting point according to which the creator has the intellectual property rights therefore still applies. However, the contractor and the employer have, of course, a right to use the design materials, descriptions, drawings, etc made, for example, by the consultant, provided that these are used in an ordinary and intended matter in connection with the construction project.
The employer’s right to use such documents (drawings, descriptions and other design material) also applies if the employer has rightfully terminated the contract, if the removal or lack of access to these documents would inflict a loss on the employer.
It is, however, occasionally seen that the parties agree on certain provisions regarding the intellectual property of the design material, etc, prepared in relation to a construction project.
The remedy available in the event of a breach of a construction contract depends on the specific circumstances, notably the severity of the breach and what the breach relates to.
With regards to termination, under Danish law a party is generally entitled to terminate a contract if there is a material breach, and such breach may express itself in many ways, just as it may be agreed beforehand in which situations a party may terminate the contract.
The AB Standards include specific provisions regarding the remedy available in different situations.
For instance, it follows from the AB Standards that an employer is entitled to demand that a subcontractor or supplier is deprived of its right to execute works and deliver materials to the construction project, if that party has failed materially to comply with applicable rules or agreed terms and conditions on social responsibility, including rules on health and safety at work. Thus, the employer has, in certain circumstances, a right to remove a subcontractor from the construction project even though the employer has no contractual relationship to that subcontractor.
Nonetheless, the most frequent scenarios are related to delay and defects, and a few notes on these situations are therefore inserted below.
The Employer’s Remedies in Relation to Delay and Defects
The most common remedy available for the employer in the case of a contractor’s delay is liquidated damages, as described in 5.3 Remedies in the Event of Delays.
Furthermore, the employer is entitled to terminate the construction contract in whole or in part with immediate effect in the event of material delay by the contractor.
With regard to defects, which are assessed at the time of handover, the employer is entitled to retain a reasonable amount as security for the rectification of defects notified at the time of handover. This amount is payable to the contractor as soon as possible after the defects have been rectified.
The contractor has both a duty and a right to rectify the defects identified at handover. However, if the contractor fails to rectify the defects within a reasonable time, then the employer is entitled to have the defects rectified at the contractor’s expense or to be granted a reduction in the contract sum.
During the project, the employer is further entitled to terminate the contract if the works are executed at such a low-quality level that the employer has reasonable grounds to assume that the contractor will not be able to complete the works without material defects.
The Contractor’s Remedies in Relation to Delay
If the employer fails to pay an amount due by the final date for payment, various remedies are available for the contractor. See also 4.2 Payment.
The contractor may stop work if the employer fails to pay an amount due. Prior written notification with three working days’ notice must, however, be submitted to the employer.
The contractor is also entitled to terminate the construction contract in the event of material delay related to the employer or delays by another contractor, provided that the employer does not make reasonable efforts to expedite the works. Other material breaches by the employer may also entitle the contractor to terminate the contract.
Provisions containing restriction of remedies are not uncommon in Danish construction contracts, but most commonly the provisions on remedies in the AB Standards are used, though often with certain nuances.
Danish construction law is, however, not as strict in its literal interpretation as other jurisdictions, and parties sometimes attempt to formulate quite one-sided remedy provisions.
Significantly one-sided provisions can be challenged and are sometimes set aside by Danish arbitral tribunals.
Sole remedy clauses where certain types of remedy are strictly excluded, etc, are not common in construction contracts in Denmark.
As described in 5.3 Remedies in the Event of Delays, liquidated damages are often agreed and entail that the employer is not entitled to claim additional damages related to that delay. This may be considered a sole remedy clause to some extent, but besides such clauses, sole remedy clauses are generally not used. Part of the explanation for this is presumably due to the excluded damages in the AB Standards, see 9.4 Excluded Damages.
In the AB Standards, certain damages are excluded from liability.
Generally, the contractor is not liable for any loss of business, loss of profit or other indirect losses resulting from defects. In relation to the contractor’s product liability, the contractor is likewise not liable for any loss of business, loss of profit or other indirect losses resulting from damage caused by a defect in a product used in the building or construction works.
Furthermore, in relation to delay caused by the employer, the employer is not liable for lost profits as a result of the contractor being unable to carry out other work in the delay period and similar ensuing losses.
Under Danish law, a party has a general right to withhold or set off payment against the other party if one has a (counter) claim. Such rights may be amended in the construction contract but are most often not amended.
As such, withholding payment or setting off a claim is a common tool for employers if, for instance, the employer has a claim against the contractor as a result of a breach.
The public courts are generally competent to adjudicate disputes in Denmark, if nothing else is agreed between the parties.
Since the AB Standards includes an arbitration clause and since the AB Standards are used in most larger construction contracts, most construction disputes are subject to resolution under the auspices of the Danish Building and Construction Arbitration Board.
The Danish Building and Construction Arbitration Board presently handles approximately 400 arbitration cases and more than 1,000 requests for expert opinions a year and is therefore highly capable and experienced.
As mentioned, arbitration is commonly used within construction disputes if the parties have based their contract on the AB Standards.
In addition to arbitration, the AB Standards include a range of alternative dispute resolution.
Dispute Resolution Ladder
The AB Standards contain a so-called dispute resolution ladder. This entails that efforts must be made to resolve and settle a dispute between the parties through negotiation, at either party’s request.
Mediation, conciliation, speedy resolution and arbitration may not be initiated before the negotiation procedure has been completed.
Mediation and Conciliation
Furthermore, at the request of either party, the Danish Building and Construction Arbitration Board will appoint a mediator with a view to settling a dispute. The parties have a duty to participate in the mediation/conciliation process, and no arbitral proceedings may be initiated or continued until the mediation/conciliation process has been completed.
Speedy Resolution
In certain cases, the Danish Building and Construction Arbitration Board can appoint a so-called umpire to make a speedy resolution at the request of a party.
Not all disputes are suitable for speedy resolution. A few examples of disputes that are suitable for speedy resolution are:
Nørregade 21
1165 Copenhagen K
Denmark
+45 33 345 000
chj@bruunhjejle.dk www.bruunhjejle.dkThe War in Ukraine and General Price Rises and Supply Issues
Overall difficulties as a consequence of Russia’s war in Ukraine
At global level, Russia and, to some extent, Belarus have been met with widespread and burdensome economic sanctions. Denmark, also a member of the EU, is no exception from this approach. Sanctions have been imposed on imports of several goods and materials, including steel from Russia and cement from Belarus. Further, exports to Russia of various products and goods, including advanced technology products such as sensors, lasers, navigational equipment, etc have been prohibited. Breach of sanctions may be penalised with fines or even imprisonment.
Besides dealing with such public restrictions, all companies have to consider the moral dilemmas and reputational risks of trading and collaborating with Russian or Russian-affiliated companies or entities or simply maintaining commercial presence in Russia. The public opinion in Denmark has – largely – been against companies who have opted to remain established in Russia since the onset of war.
The war has entailed very tangible and practical difficulties impacting the construction industry in Denmark. Production of steel and wood has been halted in Ukraine, and there are difficulties in transporting the goods still being produced and available to the market. Labour force from Ukraine has been cut off as Ukrainian men remain in the country to participate in its defence. To some extent, these practical difficulties also relate to other Eastern European countries.
The effects of shortages of supplies are exacerbated as supply lines still suffer from the impacts and challenges of the COVID-19 pandemic, and consequential price rises are accompanied by the effects of general economic inflation.
In the construction industry, the current as well as the likely further and future effects of the war must be handled with due care by all parties involved in both already concluded and new agreements.
Price rises on materials and industry uncertainty
Even before the war in Ukraine, prices of construction materials, particularly steel, wood, lumber and concrete elements, had risen significantly. From fourth quarter 2020 to fourth quarter 2021, the Danish construction cost index for housing tower blocks had risen approximately 8% for construction materials. At the time of writing, the index has not been updated; however, industry voices and bulletins suggest that current yearly price rises on construction materials may be as much as 30% in accordance with to the so-called manufacturer price index. Through 2021, the main factors limiting production in the Danish construction industry have increasingly been lack of supplies or equipment and lack of labour force.
Nevertheless, the Danish construction market is continuously characterised by a very high level of activity, but upcoming projects may face difficulties. Price rises on materials most significantly impact construction projects involving new buildings or civil works, whereas renovation projects are less prone to such impacts. Across the industry, concerns have been raised that new projects may be cancelled, and some public construction projects have already been postponed, as the tenders proved impossible to complete within budgets.
The current and undesirable cocktail of high prices of materials and energy accompanied by unsure supply lines may prove substantial, and the risk of deceleration is high. For contractors, there is an increased risk of submitting offers that do not cover expenses. For owners, the budget may, pre- or mid-project, prove to be insufficient. It has also been raised that – to some extent – a minor slowdown of activity in the Danish construction industry may counter a tendency of overheating and inflation.
For all parties involved, unforeseen price rises may be damaging to the successful execution of projects and lead to disputes or breakdown of co-operation. Danish industry actors have therefore urged that parties co-operate to resolve issues, overcome current obstacles and work together to minimise the overall effects.
Danish regulation on price increases
In Denmark, most construction projects are carried out based on fixed-price agreements. The legal point of departure is that the contractor carries the risk of even quite substantial price rises.
Under Danish construction law, the rights and obligations of the parties involved are not set out by statutory regulation but, in the absence of agreement between the parties, by the unwritten law of obligations. Virtually all construction projects of some size, including public contracts, are based on agreed documents prepared by a committee appointed by the Danish Minister for Climate, Energy and Building (and with representatives from the interest groups) (called the “AB Standards”).
The AB Standards contain indexation clauses, which to some extent may compensate the contractor for increased prices. However, the price remains fixed for works carried out within the first 12 months after the offer was given. Thereafter, indexation is applicable. Usually, a relevant index is agreed upon, typically an official construction cost index. Construction contracts may refer to other documents such as industry standard reservations, etc, which allow for compensation in case of price rises.
The AB Standards allow for adjustment of the agreed price in case of state measures (public bans and orders) leading to significantly increased or decreased prices that are not covered or compensated by other regulation, typically indexation. The state measure must be issued by a public administration after the time of the offer.
The AB Standards were updated in 2018, and the updated versions provide for financial compensation in case of extraordinary increases in prices. Previous versions (AB92, ABT93 and ABR89) do not contain such clauses. However, the parties often included said regulation by reference to other documents. To claim compensation in accordance with the AB Standards, the contractor must fulfil and document a series of criteria:
Consequently, a contractor claiming compensation must meet a quite heavy burden in terms of documentation and criteria in order to satisfy the above. Further, compensation is not full in terms of covering the price rise entirely. It is expected that future contract administration, negotiations and disputes will relate to this issue and that executing parties to some extent must remain flexible to facilitate successful completion of projects. Though the owner may in principle be entitled to refuse a contractor’s claim for compensation, there is not much gained if such refusal leads to the breakdown of co-operation or even insolvency issues.
Delayed delivery of supplies and workforce issues
Another consequence of the war and the pressured supply lines is delays in supplies of materials for the construction industry. One of the major Danish infrastructure projects, the Copenhagen Metro – Branch off to Sydhavnen – has recently announced that the project experiences difficulties in obtaining, inter alia, necessary supplies of steel. Ukraine being Europe’s largest supplier of both raw and processed steel, the war has put further pressure on global lines of supply, and the challenges are increasingly impacting Danish projects.
The AB Standards contain force majeure clauses granting the parties time but no money in case of war, unusual events of nature, fire, strike, lockout, blockade, vandalism or similar matters that are not caused by any of the parties and are beyond the parties’ control. In case of public bans and orders (change of laws), the contractor may claim both time and damages, provided of course that the ban or order is not caused by the contractor itself. The rules are equally applicable to problems of supplying the project with an adequate workforce. In such case, case law suggests that the contractor must demonstrate near-impossibility, and the problem must be unforeseeable and due to general and extraordinary events. As to complex work demanding specialist skills, it may prove easier to satisfy these demands.
Either case requires documentation and substantiation of the causal effects of the war, or the otherwise induced supply issues, and the parties have in particular a duty to mitigate effects, including loss of time. This entails a duty to seek out other suppliers and possibly similar and usable materials within the scope of the parties’ agreement. Increased costs due to such matters are i) regulated by the above-mentioned rules on price rises or ii) in case of public bans or orders, losses subject to compensation. General rules of Danish construction law encompass a threshold of sacrifice; however, the bar for meeting such level of increased expenses is very high.
New contracts and going forward
Initially, it should be noted that when entering into new contracts with the current situation at hand, a party who claims easing of obligations further down the line will have difficulties in successfully claiming the war as grounds for extension of time and/or monetary compensation, as its causal effects – at their current scale – will likely be considered foreseeable.
The legal point of departure for these matters predominantly places the risk on the contractor, and the contractor is expected to consider and take account of the war. If the war expands or further sanctions, etc are introduced, it will be debatable and based on a specific assessment if such matters should be considered foreseeable – the likely result is that the parties cannot be expected to foresee events that are developing.
The situation in Ukraine and the global challenges as to the supply of building materials are expected to cause further reservations from contractors and suppliers. In terms of public procurement issues, changes to fundamental contractual elements, such as pricing, may require repeated procurement process, if not caused by unforeseen matters. As such, the effects on projects and on the parties’ rights and obligations may impact on various levels.
It is expected and advisable that parties to future contracts actively consider and regulate the associated risks and the practical handling of these challenges. This requires clear and specific clauses, ie, on certain critical material and on the time of purchase, both in terms of pricing and timely procurement of such material. On the one hand, it is not in the parties’ interest to purchase and store material; however, in the current market, this may be advisable or even considered due diligence. Clauses should regulate pricing on materials in both upwards and downwards, and in the absence of such clause, a contractor will expectedly have to add a significant risk margin to most offers given under these circumstances.
Generally, the war and the situation of price rises and supply chain issues require more transparency, clear and specific agreements as well as increased dialogue and understanding on behalf of all parties. Looking towards the end result and the total pricing of a given project, it may prove far less costly for both contractor and owner to keep a flexible approach and acknowledge the challenges at hand.
Nørregade 21
1165 Copenhagen K
Denmark
+45 33 345 000
chj@bruunhjejle.dk www.bruunhjejle.dk