Contributed By DLA Piper Hong Kong
Key Legislation
The principal legislation governing building works in Hong Kong is the Buildings Ordinance (Cap 123) and its subsidiary legislation.
Site safety is primarily governed by the Factories and Industrial Undertakings Ordinance (Cap 59) and its subsidiary legislation including key regulations such as the Construction Sites (Safety) Regulations (Cap 59I).
The key legislation governing the protection of environment in Hong Kong includes the Air Pollution Control Ordinance (Cap 311), Waste Disposal Ordinance (Cap 354), Water Pollution Control Ordinance (Cap 358), Noise Control Ordinance (Cap 400) and the Environmental Impact Assessment Ordinance (Cap 499).
Common Law
Aside from this key legislation and regulations, the principal laws governing the construction market in Hong Kong are derived from the common law of contract and tort.
Standard form contracts are frequently used in the construction industry in Hong Kong.
Public Works
The Hong Kong Government has endorsed the usage of the NEC suite of contracts for all public works since around 2016. According to the Practice Notes for New Engineering Contract (NEC) – Engineering and Construction Contract (ECC) for Public Works Projects in Hong Kong published by the Development Bureau updated in August 2021, the application of NEC has been extended to public works project procurement after 2016 and the decision and justification as to whether or not to adopt NEC in capital work contracts should be documented and endorsed by public officials.
For projects before 2016, the Hong Kong Government’s own standard forms, the Government of Hong Kong General Conditions of Contract (1999 edition) and the various versions covering civil engineering works, building works and electrical and mechanical works, design-and-build contracts and team contracts were commonly used for contracts with the contractor, while the Government of the Hong Kong Special Administrative Region Subcontract for Building Works (2000 edition) was commonly used for contracts between the contractor and the subcontractor.
For railway projects, the Mass Transit Railway Corporation has its own set of contract documents.
Private Works
For private works, the Standard Form of Building Contracts (published by the Hong Kong Institute of Architects and the Hong Kong Institute of Surveyors) and the Standard Form for Domestic Subcontract (published by the Hong Kong Construction Association) are frequently adopted to govern employer-contractor and contractor-subcontractor relationships.
Some contractors prefer to use their own standard forms available in the local Chinese language, particularly for contracts with local subcontractors/suppliers.
International Projects
The International Federation of Consulting Engineers (FIDIC) standard forms of contracts are widely used in construction projects involving international elements and are used in many construction projects in mainland China involving Hong Kong parties.
The COVID-19 pandemic had a comparatively less significant impact on the construction market in Hong Kong compared to other jurisdictions.
The Hong Kong government had implemented various quarantine and public health safety measures since early 2020. Some projects had been affected by delays caused by material and equipment shortages, and workers and key personnel had been impacted by travel bans. However, the most significant impact was only seen after the "fifth wave" of cases brought about by the Omicron variant hit the city in February/March 2022.
Employers in Hong Kong
The largest employer for construction projects in Hong Kong is the Hong Kong Government. The construction market in Hong Kong is also driven by projects initiated by listed local developers as employers.
Employers’ Rights and Obligations
The employers’ rights and obligations are generally governed by the contracts entered into between the employers with their contractors and/or consultants.
In general, the employer’s obligations in a typical building contract in Hong Kong usually include:
The employer’s rights in a typical construction contract in Hong Kong usually include:
Relationships Between the Employers and Other Parties
In most construction projects in Hong Kong, architects/designers, engineers and/or quantity surveyors would be engaged by the employers for the administration and supervision of the building contracts with the contractors.
Employers do not generally enter into direct contractual relationships with the subcontractors unless separate warranties/guarantees are executed by the subcontractors and some subcontracts may give rights to the employer for making direct payment to the subcontractors if payments had been withheld by the contractors.
Contractors in Hong Kong
Contractors working on public works in Hong Kong are controlled by an approved list of contractors maintained by the Development Bureau. The contractors are classified into different categories according to their experience and capabilities and many of the public works projects require the contractors, or at least one of the contractors in a joint venture submitting a tender to the project, to be in a certain category to qualify.
For private works, the contractors must be registered in the appropriate categories of registered contractors under the Building Ordinance (Cap 123) in Hong Kong.
Contractors’ Rights and Obligations
Contractors’ rights and obligations are generally governed by the construction contracts between employers and contractors.
In general, the contractor’s obligations in a typical building contract usually include:
The contractor’s rights in a typical building contract in Hong Kong usually include (but are not limited to):
Relationships Between the Contractors and Other Parties
A typical building contract generally requires the contractor to comply with the the instructions of the architect/designer/engineer or other consultants appointed by the employer.
Relationships between the contractors and the subcontractors are typically governed by the relevant subcontracts between the contractors and the subcontractors. The subcontracts very often will provide that the subcontractor is bound to the terms of the subcontract and the main contract and that payment to the subcontractor is contingent upon payment to the contractor by the employer.
Subcontractors in Hong Kong
Subcontractors in Hong Kong are typically smaller local companies specialised in a particular nature or trade of works.
Subcontractors’ Rights and Obligations
A subcontractor is typically required to execute the subcontract works in accordance with the requirements under the main contract between the contractor and the employer and to suit the contractor’s programme, and the subcontractor is typically entitled to receive payment after the contractor has received payment from the employer.
Relationships Between the Subcontractors and Other Parties
The relationships between the contractors and the subcontractors are typically governed by the relevant subcontracts between the contractors and the subcontractors.
There are usually no direct contractual relationships between the employers and the subcontractors unless the subcontractors are required to execute separate warranties with the employer. The subcontractors are, however, very often bound to both the subcontract and the main contract under the terms of the subcontracts and many subcontracts give rights to the employer for making direct payment to the subcontractors if payments had been withheld by the contractors.
Financiers in Hong Kong
Financiers in Hong Kong are typically commercial banks or institutional investors.
Financier’s Rights and Obligations
The financier is not usually a party to the construction contract although a financier may require the employer to submit the relevant construction contracts for its approval to ensure there are sufficient safeguards to control the time and costs incurred for the construction project.
Relationships Between the Financier and Other Parties
The relationships between the financiers and the employers are typically governed by the relevant loan/facility agreements and securities executed by the employers. There are normally no direct contractual relationships between the financiers and the contractors or the subcontractors.
The scope of works in a construction contract is typically set out in the general and technical specifications and the relevant drawings forming part of the construction contracts, and as amended and supplemented by the architect/engineer appointed by the employer.
Scope for Variations
The scope for variations is typically determined by the instructions or confirmation of oral instructions issued by the employer and/or the architect. For instance, the Standard Form of Building Contracts published by the Hong Kong Institute of Architects and the Hong Kong Institute of Surveyors (2005 edition) (“HKIA/HKIS Standard Form 2005”) provides that the instruction requiring a variation shall describe the change required to the design, quality or quantity of the works or the imposition of, or change to, any obligation or restriction on the contractor.
Price for Variations
The price of variations is typically determined by reference to agreed contractual rates and in the absence of such agreed rates at fair rates or daywork. For instance, the HKIA/HKIS Standard Form 2005 provides that:
Variations Requested by Contractors
The construction contract would typically provide that the contractor shall not carry out work involving a variation without a written instruction from the architect/the employer or confirmation of an oral instruction except in the event of emergency.
Depending on whether the contract between the employer and the contractor is a design-and-build contract or a build-only contract, the division of design responsibilities among the employer, the architect/designer, the contractor and other consultants will vary depending on the terms of the relevant building and service contracts.
In a design-and-build contract, the contractor’s design obligation is usually more extensive and the contractor will be required to ensure that the design and works are reasonably fit for purpose. By contrast for a build-only contract, the contractor is usually only required to follow the instructions of the employer, architect/designer or other consultants on the design and its design responsibilities may be limited to designing the temporary structures, shop drawings and to exercise reasonable care.
The Employer, the Architect and the Authorised Person
The employer usually enters into a contract with an architect/engineer to plan and design a project and to coordinate with the contractor and other consultants such as the designers, engineers, surveyors, etc. The architect/engineer often plays an important role in the administration of a construction project with responsibility to issue instructions/variations/certificates for and on behalf of clients and for inspection and acceptance of work, etc.
An authorised person who is an experienced building professional registered under the Buildings Ordinance (Cap 123) has to be appointed for submission of the building proposals to the Building Authority for approval and the appointed authorised person is responsible for supervising the carrying out of the building works and notifying the Building Authority for any contravention of the approved plan of any building regulations.
The Contractor and Subcontractors
The main contractor is usually responsible for completing and delivering the works according to the contractual requirement and coordinating the work of subcontractors to ensure satisfactory and timely completion of the works. The subcontractors are responsible for completing and delivering the subcontract works according to the subcontracts with the main contractor.
The responsibilities for the status of the construction site are generally determined contractually by the parties.
The risk of unforeseen ground conditions is usually borne by the contractor. For instance, the Hong Kong Government’s General Conditions of Contract for Civil Engineering Works provides that the contractor is deemed to have examined and inspected the site and its surroundings and to have satisfied himself, before submitting the tender, as regards to the roads or other means of access to the site, the nature of the ground and sub-soil, the form and nature of the site, the risk of injury or damage to property, the nature of materials to be excavated, etc.
Most standard form contracts also provide that the contractor is responsible for complying with statutory requirements including the relevant legislation regarding pollution.
Archaeological finds and discoveries of antiquities are, however, usually considered as events that are the fault/responsibility of neither of the parties and may be a ground for the contractor to apply for extension of time (eg, the HKIA/HKIS Standard Form 2005).
All construction projects in Hong Kong must be approved by the Building Authority. Other approvals may also be needed from other government departments depending on the nature of the construction works such as the Fire Services Department, the Water Services Department, the Drainage Services Department, the Electrical and Mechanical Services Department, etc.
The Authorised Person is responsible under the Building Ordinance (Cap 123) to submit the building proposal to the Building Authority for approval. The building contract usually also provides that the contractor shall co-operate and assist the employer to obtain all necessary permits for the project.
The contractor is typically responsible for the care and maintenance of the works during the construction period and until the end of the agreed defects liability period. Upon completion and the end of defects liability period, maintenance works are typically governed by separate maintenance contracts and/or warranties.
The landlords or building owners have duties to maintain their properties under common law. The duty for maintenance may also be found in the deed of mutual covenant and other legislation for fire, water, electrical and other utilities installations.
Employers in Hong Kong do not usually intervene with the operation and finances of their contractors or consultants but building contracts in Hong Kong typically contain express clauses prohibiting transfer or assignment of building contracts.
All new buildings are required to obtain an occupation permits (OP) before completion.
To obtain the OP, the registered building contractor has to submit to the authorised person for endorsement a completed and signed form to certify that the building has been constructed in accordance with the Building Ordinance (Cap 123) and the drawings and plans approved by the Building Authority. Inspections will be arranged and the Building Authority will decide if the OP can be issued and if not, what work has to be done before it can be issued.
The tests required for certified completion of the works are determined by the terms of the construction contract. Typically, the contractor is required to provide all vouchers, test certificates or other evidence to satisfy the employer/architect that the materials and goods comply with the contract specifications and to carry out all tests and inspections specified in the construction contract or instructed by the employer/architect to satisfy the employer/architect that the works had been practically/substantially completed.
Practical completion means that the works are fully completed to a state that permits the employer to enter into full beneficial occupation save for very minor items of work left incomplete. Substantial completion is completion to a state that permits the employer to enter into functional or operational occupation save for minor outstanding works to be completed in the maintenance period.
The architect/engineer will certify for practical/substantial completion if it considers that the works can be considered as practically/substantially complete, which permits the employer to take possession of the works and marks the beginning of the defects liability period. The contractor is then considered to have delivered the works and its liability to pay for liquidated damages for late completion may cease.
Length of Defects Liability Period
The length of the defects liability period depends on, and are generally agreed upon, in the terms of the building contract between the employer and the contractor. The defects liability period usually ends in 12 to 24 months after substantial completion of the project. For the HKIA/HKIS Standard Form 2005, the defects liability period will be 12 months from substantial completion if it is not agreed and stated in the appendix.
Remedies for Defects During Construction
If defective work or design is discovered before practical/substantial completion, the construction contract may provide the right for the employer/architect to order further testing and inspection, to direct removal or replacement of the defective work or design, to vary the work or to engage a third party to rectify the defective work or design and make an adjustment/ set-off to the contract price.
Remedies for Defects After Practical Completion
After practical/substantial completion, the contractor is required to rectify the defects, which are usually listed out in the defect list that accompanies the certificate of practical/substantial completion, and the employer is usually entitled to call for the contractor to return to the site to repair or to make good defects that were discovered during the defects liability period.
The employer is entitled to claim for the cost of making good and repair for defects in the works or in the design and consequential damages such as compensation for loss of use or liabilities incurred towards third parties.
Remedies for Defects After Final Certificates
Most standard form contracts provide that the architect/engineer will issue the defects rectification certificate or making-good certificate upon the expiry of the defects liability period when it is satisfied that the contractor has satisfactorily completed all unfinished works and all defects have been rectified.
The architect/engineer will typically be required to issue the final certificate after the issuance of the defects rectification/making-good certificates and the signed final account. The final certificate will generally indicate that the employer has accepted and is satisfied with the quality of work is concerned save for latent defects or omissions not reasonably discoverable at the time of the defects rectification/making-good certificate. For instance, the HKIA/HKIS Standard Form 2005 provides that the final certificate is a conclusive evidence that the materials, goods, workmanship and work were provided or carried out to the architect’s satisfaction.
The employer may therefore not be able to claim for defects or omissions after the final certificate unless they are latent defects or omissions not reasonably discoverable.
Notification of Defects
According to the Limitation Ordinance (Cap 347), the limitation period for a contractual claim founded upon a simple contract (ie, not under seal) is six years from the date of accrual of the cause of action.
The limitation period in respect of a simple contractual claim for defects runs from the date of practical/substantial completion of works except for limited circumstances where the limitation period is extended such as acknowledgement, if the action is based upon the fraud of the defendant, deliberate concealment, mistake, etc. If the employer did not commence action for defects within six years, its contractual claim for defects may be time-barred.
The limitation periods for actions of tort is six years from the accrual of the cause of action but actions in respect of latent defects can be brought within three years from the date of knowledge subject to a maximum long stop date of 15 years from the date of accrual of the cause of action.
Lump Sum Contract
For this type of contract, the contractor will carry out works based on the plans, drawings and specifications for an agreed price and the agreed basis on which the agreed lump sum will be subject to adjustments, such as due to variations instructed by the employer/architect and/or fluctuations.
Measurement Contract
A measurement contract allows the interim payments and the final contract sum to be ascertained by measurement and valuation by reference to the bills of approximate quantities or a schedule of rates agreed under the contract.
Cost-Reimbursement Contract
This type of contract provides that the cost will be paid based on actual cost incurred including for materials, labour, plants and equipment plus an agreed percentage for overheads and profits. The contractor may be required to submit regular cost estimates and reports on cost incurred to avoid excessive and unreasonable expenditures.
Most standard form contracts specify the timeframe for the employer to make payment to the contractor (usually upon issuance of a certificate by the architect/engineer) and provide the contractor with the right to terminate the contract if the employer fails to make payment regularly. Some contracts may provide that the contractors are entitled to charge interest at an agreed rate for late payment.
Interim payments are provided in most standard form contracts and are generally used. Advanced payments and delayed payments are less commonly seen but not unheard of.
Contractors are typically required to submit applications for interim and final payments along with supporting documents to the architect/engineer/quantity surveyor for assessments and certifications.
Role of Employer, Contractor and Other Parties
The main contractor is typically responsible for co-ordinating with the subcontractors and consultants and submitting and updating a master programme and relevant method statements for the construction works to ensure timely completion of the construction work.
The architect/engineer appointed by the employer is typically responsible for monitoring the contractors’ progress of work.
Planning Safeguards
In most standard form contracts, the employer is entitled to impose liquidated damages if the contractor fails to deliver its work by the completion date. Although not commonly seen, the contract may also provide an incentive bonus for early completion.
Interim payments are typically made based on the amount of work done certified by the architect and some contracts, depending on the nature of work, may also provide for milestones and milestone payments.
If the event of delay is one of the specified events in which extension of time can be granted by the architect/engineer under the contract, the duty to set in motion the extension of time procedures usually rests with the contractor by giving notice of delay.
The architect/engineer receiving the notice of delay is required to decide whether the delay is an event specified under the building contract, for which the contractor is entitled to an extension of time and the overall extension of time that he considers that the contractor is entitled to.
If the event of delays is caused by the contractor’s own action and/or inaction – eg, such as failure to secure sufficient labour, material or equipment – the contractor is not entitled to extension of time or damages from the employer and the contractor should carry out delay recovery measures or otherwise risk liability for liquidated damages for delayed completion.
The employer is typically entitled to claim liquidated damages, which is normally a daily rate for compensation for financial and other losses resulting from delayed completion.
Most standard form contracts also entitle the employer to terminate the contractor’s employment if the contractor fails to proceed with the works regularly and diligently.
Most standard form contracts commonly used in Hong Kong require the contractor to give a notice of delay to the architect/engineer stating the cause and identifying the listed event specified in the construction contract, the estimated length of the delay and any material circumstances as the first step for a request for an extension of time. The contractor is then typically required to make further submissions at specified intervals to give further substantiations and updates to the effect of the delaying event.
The contractor is typically required to submit such notices of delay within a certain time upon the occurrence of the event of delay. For instance, the HKIA/HKIS Standard Form 2005 requires the contractor to submit the first notice of delay within 28 days of the commencement of an event likely to cause delay to the completion of the works and to give a second notice within 28 days of the first notices and further submissions at intervals not exceeding 28 days until the delay ceases.
Many construction contracts will further provide that it shall be a condition precedent that the notices of delay be submitted within the specified timeframe for any extension of time requests by the contractor.
The term "force majeure" is used to describe situations where an unforeseeable event, generally outside the control of the parties, makes execution of the contract impossible (or almost impossible) during the contract period. However, the term has no established meaning under Hong Kong law and each force majeure clause must be examined individually based on the facts of each case to determine its meaning.
It is possible to contractually limit or exclude certain circumstances from being qualified as force majeure by clear wordings and clear definitions of what constitutes a force majeure event.
An unforeseen circumstance or event that renders the construction contract physically or commercially impossible to perform, or transform the obligation to perform into one radically different than envisaged at the time of contracting, may frustrate the construction contract. However, it is a narrow doctrine and is applied strictly in limited circumstances.
Whether the construction contract has been frustrated is to be established according to common law. The consequences of frustration are set out in section 16 of the Law Amendment and Reform (Consolidation) Ordinance (Cap 23).
According to the Control of Exemption Clauses Ordinance (Cap 71) (“CECO”), liability for death or personal injury resulting from negligence cannot be contractually excluded or limited. The exclusion or restriction of liability for other loss or damage resulting from negligence must satisfy the requirement of reasonableness.
According to the Misrepresentation Ordinance (Cap 284), any contract term excluding or exempting liability or any remedy for misrepresentation must also satisfy the same test of reasonableness stated in the CECO.
The concepts of wilful misconduct and gross negligence exist in Hong Kong and the interpretation of such terms in a contract is governed by applicable case law.
It is possible for the parties to contractually limit their liability subject to the statutory control set out in 6.1 Exclusion of Liability.
Limitation of liabilities are more commonly seen in contracts for smaller projects or for agreements between the employer and its consultants and are generally limited to the amount of the consultancy or service fees paid by the employer.
Indemnities are common provisions used and negotiated by parties to limit risk.
The most common types of indemnities found in standard form contracts are indemnities against injury or death to any person and injury or damage to real or personal property and claims by third parties for breach of intellectual property rights.
Surety Bonds
The contractor is typically required to obtain a guarantee from an insurance company or a bank approved by the employer/architect for the due performance of the construction contract under the terms of a surety bond. The surety bond is procured by the contractor by paying a premium.
The surety bond is typically an undertaking from the insurance company or bank to pay the employer up to a stated limit if the contractor fails to discharge its contractual obligations under the building contract.
The surety bond can be: (i) a conditional bond, which may require the employer to establish the default and/or the damages occasioned by the breach of the construction contract; or (ii) an on-demand bond, which the employer may only be required to make a written demand to the bondsman without proof of default by the contractor.
Payment Bonds or Parent Company Guarantees
The contractor may also request for a payment bond or a parent company guarantee to guarantee that the employer will make payment according to the terms of the construction contract, especially where the employer is a special purpose vehicle established for the purpose of the construction project only.
Similarly, the employer may also request a parent company guarantee from the contractor to guarantee performance of the construction contract if the contractor is a small subsidiary of an established contractor.
The contractor is typically required to and will effect and maintain:
If the construction works involve the erection of a new building or the alteration of an existing building, it is common for the employer to effect and maintain insurance against the building.
In most standard form contracts commonly used in Hong Kong, insolvency of the employer or the contractor typically entitles the other party to terminate the construction contract.
The termination clause typically gives the employer a right to enter upon the site and to use plant and materials left over for the completion of the works.
The NEC 3 standard forms now commonly used in contracts for public works allow the employer and the contractor to share the risk of any delay caused by a ‘compensation event’, which refers to an event that stops the contractor from completing the construction works, which neither party could prevent.
The target cost contracts of the NEC 3 standard forms allow the risk to be shared between the employer and the contractor further. Under these types of contracts, the contractor gains a bonus if the actual cost is below the target cost but shares the cost if it goes above the target costs.
Other common standard form contracts typically define and specify the perceived risks and allocate responsibilities to either the employer or the contractor. The risks that are typically agreed to be shared between the employer or the contractor are usually events that are faults of neither parties such as force majeure, inclement weather, etc.
Most standard form contracts, such as the HKIA/HKIS Standard Form 2005, require that the contractor’s site management team to have appropriate qualifications, seniority and experience to properly organise, manage, plan supervise and co-ordinate the carrying-out of the construction works.
Appointment of key management and technical positions may require the approval of the employer/architect and the employer/architect may be entitled to instruct the contractor to replace any incompetent personnel.
The construction contract may require the contractor to obtain the employer’s written consent before engaging all domestic subcontractors or for certain specialist trades of works.
The contractor may also only object to the employer’s nomination of subcontractor on grounds such as poor safety record, financial standing or technical competence.
The contractor is typically required to pay the cost of all royalties and licence fees for the design and the use of intellectual property in respect of any materials, goods, plant and equipment used and to indemnify the employer against all claims for any infringement of intellectual property rights in the contractor’s design or use of materials, goods, plant and equipment.
For design-and-build contracts, the contractor may retain the intellectual property rights of the design of the project and know-how generated throughout the course of the project.
The usual remedy for breach of construction contract is an award of damage to compensate the innocent party for damage, loss or injury suffered as a result of the breach. Damages may also be awarded for losses consequential upon the breach.
Where a breach is repudiatory, the innocent party may choose to accept the repudiation and rescind the construction contract and claim for damages or to continue with the contract.
Specific performance may be available to the innocent party although the court will not normally grant such equitable relief where damages will adequately compensate the claimant or where the court cannot properly supervise performance.
Injunctive relief may also be available in some circumstances, for instance for breach of confidentiality obligations, to the employer for evicting the contractor from the site upon termination of the contract, or to the contractor to restrain the employer from exercising the power to terminate and evict the contractor, etc.
Depending on the terms of the construction contract, other remedies such as suspension of work or determination of the contract upon notice may also be available.
The standard form contracts commonly used in Hong Kong do not typically contain standard clauses limiting remedies available to a party.
Sole remedy clauses are not commonly used in construction contracts in Hong Kong.
Most standard form contracts, for instance the HKIA/HKIS Standard Form 2005, typically provide that the contractor may only claim for direct loss and expense for disruption/prolongation claims, ie does not include indirect or consequential loss or damages.
Retention and suspension rights are not generally contractually excluded in construction contracts in Hong Kong.
Retention Rights
The standard form construction contracts commonly used in Hong Kong usually expressly provide for the employers’ rights to retain payment at the agreed percentage such that the employers may have recourse to it for payment of any amount they are entitled to under the building contracts.
Suspension Rights
The standard form construction contracts commonly used in Hong Kong also usually expressly provide for the employers’ rights to suspend the building works although the contractors may be entitled for extension of time and/or to determine the building contract if the suspension had continued for a certain period of time.
District Courts
The District Courts in Hong Kong have jurisdiction to hear civil disputes (including construction disputes) of a value over HK$75,000 but not more than HKD$3 million.
Disputes over HKD$3 million should be submitted to the Hong Kong Court of First Instance.
Court of First Instance
The Construction and Arbitration List was established within the Court of First Instance to facilitate the disposal of cases concerning:
Construction disputes are typically commenced under this list although a party or the judge in charge may request a case to be transferred in and out of the list.
Mediation
Mediation is encouraged in all civil litigations in Hong Kong. Parties in litigation have to follow the Practice Directions 31 issued by the Hong Kong judiciary to file mediation notices, responses and certificates to the Hong Kong Court and may face cost consequences if they refuse to mediate without cause.
The Mediation Ordinance (Cap 620) provides a regulatory framework in respect of certain aspects of mediation.
Arbitration
The standard form contracts commonly used in Hong Kong typically contain an express agreement to arbitrate disputes arising from the building works and most construction disputes in Hong Kong, including public works and larger-scale projects, are resolved by arbitration.
The principal legislation governing arbitration in Hong Kong is the Arbitration Ordinance (Cap 609).
Expert Determination
Some construction contracts in Hong Kong also provide a mechanism for parties to submit the disputes for determination by a third-party expert appointed by the parties.
25th Floor
Exchange Square Block 3
8 Connaught Place
Central
Hong Kong
+852 2103 0808
+852 2810 1345
may.ng@dlapiper.com www.dlapiper.com